Bahrain

Contract Price, Interim Payment and Price Changes in Bahrain Contracting Works

The Civil Code promulgated by Decree-Law 19 of 2001 (the Civil Code) regulates the contract price in contracting works, including when it is due, payment for completed parts of the work, a price that was not fixed in advance, changes in cost, estimates and design, and the owner's default and termination. Article references below are to the Civil Code.

When the price is due and how it is fixed

The contractor is entitled to the price when the work is taken over, unless agreement or custom provides otherwise (Article 599). If the price was not fixed in advance, it is determined by reference to the value of the work and the contractor's costs (Article 601).

If the work consists of several parts, or the price is fixed on the basis of a unit, the contractor may collect from the price the amount corresponding to the work he has completed after it has been inspected and accepted, provided that what is completed is a distinct part or a section of enough importance in relation to the work as a whole, unless agreed otherwise. What the price was paid for is presumed to have been inspected and accepted, unless it is proved that the payment was on account or custom provides otherwise (Article 600).

Changes in cost, estimates and design

A rise or fall in the cost of the work does not affect the extent of the obligations under the contract, without prejudice to Article 130 (Article 602). Under Article 130, if exceptional general circumstances that could not be foreseen when the contract was made arise after the contract and before it is fully performed, and as a result performance, though not impossible, becomes burdensome for the debtor so that it threatens him with grave loss, the judge may, after balancing the interests of both parties, reduce the burdensome obligation to a reasonable level by narrowing its scope or increasing its consideration, and any agreement to the contrary is void (Article 130).

If the contract is concluded on the basis of an estimate and it becomes clear during execution that the estimate must be exceeded by a large margin, the contractor must promptly notify the owner, stating the increase in the price that this entails, otherwise he loses the right to claim the increase. In that case the owner may withdraw from the contract and stop execution, provided he does so without delay and pays the contractor the value of the work completed, assessed under the contract terms, without compensating him for what he could have earned had he completed the work (Article 612). Where a lump sum was fixed on the basis of a design prepared and agreed with the owner, the contractor may not claim any increase because of a change or addition to the design, unless it results from the owner's act or is authorised by him (Article 613).

The owner's default and termination by the owner

If carrying out the work requires the owner to perform a particular act and he does not do so in good time, the contractor may call on him to perform it within a reasonable period the contractor sets. If that period passes without the owner performing, the contractor may request termination of the contract, without prejudice to his right to compensation where it applies (Article 594). The owner may terminate the contract and stop the work at any time before it is completed, but must compensate the contractor for all the expenses he incurred, the work he completed and what he could have earned had he completed the work. The court may reduce the compensation for the lost earnings if the circumstances make that reduction fair (Article 611).