The Three Legal Frameworks of a Data Center Site
A data center site in Bahrain rests on three interlocking frameworks: land tenure by ownership or industrial lease; building permits and infrastructure cost recovery; and power, water and telecommunications interconnection. Each is governed by its own legislation. Tenure is governed by Legislative Decree No. (2) of 2001 and Council of Ministers Decision No. (43) of 2003 for non-Bahrainis, by the Civil Law and the Real Estate Registration Law issued by Law No. (13) of 2013, and by Legislative Decree No. (28) of 1999 for industrial zones. Building is governed by Legislative Decree No. (13) of 1977 and Legislative Decree No. (25) of 2015. Utilities are governed by Legislative Decree No. (1) of 1996 and the Telecommunications Law issued by Legislative Decree No. (48) of 2002.
Foreign Ownership of Real Estate
Non-Bahrainis, whether natural or legal persons, may own constructed properties and lands in Bahrain by one of the legally recognized means of disposal or by inheritance, without prejudice to the right of Gulf Cooperation Council citizens, in the areas and on the conditions set by a Council of Ministers decision, under Article One of Legislative Decree No. (2) of 2001. Article Two allows commercial, industrial and tourism companies and other banking and financial institutions wholly owned by non-Bahrainis and licensed to practise their activity in Bahrain to own constructed properties and lands to establish the economic projects they are permitted to carry out, subject to three conditions: the purpose of their establishment must be a commercial, industrial, financial, tourism, health, educational or training facility or using Bahrain as a principal centre for investing their funds in activities related to the distribution of the goods they produce or the services they provide or other economic and investment projects or any other activities set by a Council of Ministers decision; the property must be allocated in the areas set by a Council of Ministers decision for the permitted activity; and its area must suit the activity as determined by the competent authority. Any disposal made in breach of this law is void, has no legal effect and may not be registered, under Article Three.
Council of Ministers Decision No. (43) of 2003 set the permitted areas, and Decision No. (67) of 2006 replaced its Article One, allowing ownership in residential building areas of categories (A), (B) and (C) throughout the Kingdom and in tourism and investment projects of a special nature after the approval of the Ministerial Committee for Public Facilities. Decision No. (48) of 2023 added a paragraph allowing platinum residency holders to own properties not listed in the decision, except areas set by a decision of the Minister of Justice, Islamic Affairs and Endowments after the approval of the Crown Prince and Prime Minister. The accompanying area maps are replaced by later decisions; Decision No. (27) of 2025 replaced them and added the Bilaj Al Jazayer project to the schedule of investment and tourism areas and projects. Article Three of the 2003 decision also allows companies and institutions wholly owned by non-Bahrainis and licensed for industrial activities to own properties in the industrial zones to establish their projects, with the usufruct of zones governed by Legislative Decree No. (28) of 1999 subject to that law.
Sale and Real Estate Registration
A sale in the Civil Law is a contract transferring ownership of a thing or another financial right for a cash price, under Article (381). A sale contract alone does not transfer title against third parties before registration: Article (17) of the Real Estate Registration Law issued by Law No. (13) of 2013 requires registration in the real estate register of all disposals creating, establishing, transferring or extinguishing original or accessory real property rights, and of final court judgments establishing any of that, and acknowledgments of waiver of the registration rank of accessory in-rem rights. If not registered, those rights do not arise, are not established, do not pass, do not change and do not lapse, neither between the parties nor against others. Unregistered disposals have no effect beyond personal obligations between the parties, under Article (18).
Leasing in the Industrial Zones
Industrial zone land is exploited by lease under Article (15) of Legislative Decree No. (28) of 1999. Contracts are drawn up through the Industrial Zones Directorate at the Ministry on the prepared models and must include a clause referring any dispute arising from the contract to arbitration if both parties agree; the Minister may, where necessary, conclude contracts on special terms under the controls set by the executive regulation. The lease term may not exceed fifty years unless otherwise agreed; and lease contracts must be notarized at the notarization office of the Ministry of Justice and Islamic Affairs, with the tenant alone bearing the notarization fees. The zones are exploited for the industrial, craft and industry-related activities set by a decision of the Minister under Article (5), and the investor must start executing the project within one year of receiving the land plot according to the specifications, conditions and drawings on which the allocation decision was based, and may not change the project or introduce any amendments without the Ministry's written approval. Article (26), as replaced by Law No. (25) of 2026, sets fifteen obligations for the industrial plot tenant: paying the rent due on time, and on repeated breach of this obligation the tenant may be required to provide a cash security equal to the rent for up to one year after paying in full the rent due because of the delay; obtaining the building licence within the period set by the executive regulation; commencing establishment of the project within the period set by the executive regulation; completing the construction, building and equipping of the facility within the period set by the executive regulation; starting operation of the facility within the period set by the executive regulation; exploiting the whole plot or industrial facilities for their designated purposes; not assigning the lease of the plot or industrial facility and not mortgaging any real right over it without the Ministry's written approval; not leasing the plot or industrial facility or any part of them to others without the Ministry's written approval; appointing an engineering office to assess the industrial facility technically and determine the aspects of restoration and construction as the executive regulation provides; carrying out the restorations needed for the facilities erected on the plot under contract based on the engineering office's report, and the Ministry may intervene where necessary to carry them out and appoint the experts needed for them, these expenses being collected by the methods prescribed in this Law; fencing the industrial plot and placing signs on the entrance as the executive regulation provides; providing internal car parks and planting them with trees according to the purposes the project practises, with the executive regulation determining the areas needed for each project and the specifications required for these parks; removing waste promptly and complying with environmental protection standards while promoting green environment values and sustainable development and encouraging the use of environment-friendly technologies; complying with occupational health and safety procedures in the facility; and complying with all studies and plans submitted to the Ministry relating to construction, operation or adjustment of the plot's status, and other plans and studies approved and endorsed by the Ministry.
Industrial facilities and equipment may not be expropriated except by a Council of Ministers decision and against fair compensation to the investor, under Article (8) as replaced by Law No. (25) of 2026. The tenant may assign the lease to others with the Ministry's approval while remaining jointly liable with the assignee for financial obligations preceding the assignment; subleasing is not allowed except with the Ministry's written approval; occupation of the property by branches of the same establishment or because of a change in its legal form, expansion or merger is not a sublease; and neither assignment nor sublease is effective against the Ministry or third parties except from the date the disposal is notarized, under Article (21). Subject to Article (33) bis, the Ministry may rescind the contract without need for a court judgment in the eleven cases set by Article (32) as replaced by Law No. (25) of 2026, including the tenant's default on paying rent at its fixed time or refusal to pay the security under item (1) of Article (26), failure to obtain the building licence, to commence the licensed project, to complete construction, building and equipping, or to start operation within the periods set by the executive regulation without an excuse accepted by the Ministry, stopping work at the facility for more than six months without an excuse accepted by the Ministry, using the plot or industrial facility for other than its designated purposes despite warning, assigning the lease, mortgaging any real right, or leasing the plot or facility or any part of them to others without the Ministry's written approval, failure to comply with all studies and plans submitted to and approved by the Ministry without an excuse accepted by it, and the tenant's death before the contract term ends without the heirs or one of them wishing to continue the lease with the Ministry. Unless the contract provides otherwise, the Ministry may, on rescission of the contract or expiry of its term without renewal, retain the buildings and facilities against compensation to the tenant, all according to the rules and procedures set by the executive regulation; and the tenant must vacate the plot of any movables after rescission or expiry without renewal, immediately or within a grace period the Ministry sets, failing which the Ministry may move them to places it determines at the tenant's expense or dispose of them while retaining the net proceeds for him, according to the controls and procedures set by the executive regulation. Also subject to Article (33) bis, on breach of the Law, its executive regulation or the decisions issued under it, the Ministry orders the violator by a reasoned decision, notified by registered letter with acknowledgment of receipt or by an electronic means, to stop the violation and remove its causes and effects within a period it sets; if he does not comply, it may take any of the measures and penalties of Article (33) as replaced by the same Law: suspending commercial registration for up to six months, closing the industrial facility for up to six months, imposing a total administrative fine not exceeding fifty thousand dinars whose calculation method the executive regulation organizes and which is collected by the methods prescribed for collecting sums due to the State, raising the rent for the violating or unexploited parts and amending the lease as to the rent clause where the tenant wishes to continue benefiting from them, according to the controls set by the executive regulation, rescinding the lease without need for a court judgment, withdrawing the violating or unexploited parts from the tenant and amending the lease as to the plot area, according to the controls set by the executive regulation, or closing the industrial facility permanently. The Ministry may publish a statement of the established violation by the means and manner the decision determines, proportionate to the gravity of the violation, but only after thirty days pass on the Ministry's decision establishing the violation without challenge or on a final judgment establishing it, as the case may be.
Building Permits and Infrastructure Cost Recovery
No building may be constructed, no works erected, no part added to them or demolished, and no alteration made by extension, raising or support, and the features of no land may be changed by excavation or filling, except after obtaining a licence from the municipality, without prejudice to Law No. (3) of 1975 on public health, under Article (1) of the Building Regulation Law issued by Legislative Decree No. (13) of 1977. Any building or work subject to licensing carried out without a licence or in breach of its terms entitles the municipality to order it stopped immediately, without prejudice to imposing the fine or removing what was done in breach; the violator is not permitted to resume work under the licence terms until the effects of the violation are removed within no more than three months from the date the judgment is pronounced, at his expense, failing which the municipality removes them at his cost, under Article (2).
Legislative Decree No. (25) of 2015 recovers the cost of creating and developing infrastructure in urbanization areas. Excluded are lands and homes owned by Bahrainis and allocated to their housing in new and existing urbanization areas, and homes owned by Bahrainis and allocated to house their first-degree relatives in existing urbanization areas whose facilities will be developed, upon submission of supporting documents and without prejudice to their obligation to pay infrastructure connection service fees, under Article Two. The cost is calculated against three services under Article Three: creating infrastructure facilities in new urbanization areas with no facilities or incomplete ones; developing and improving facilities in existing urbanization areas; and infrastructure facilities in existing urbanization areas where they exist. The cost for the first two services is collected by notifying the owners and setting the due date and payment method according to the mechanism adopted by the Ministerial Committee; the cost for the third is collected when a building permit application is filed according to the classification of the urbanization area or the purpose of the building, under Article Five. Infrastructure covers the main and subsidiary networks for roads, electricity, water and sewerage, public squares and parking, street beautification and greening works and green areas, and other facilities achieving the same purpose designated by a Council of Ministers decision on the recommendation of the Ministerial Committee.
Power and Water
Under Article (2) of Legislative Decree No. (1) of 1996, the Ministry is competent to produce, develop, transmit, distribute and sell electrical power for all purposes, and to extract, produce, distill, desalinate, store, deliver, distribute and sell water for drinking and for domestic, commercial and industrial uses; except for personal-use cases organized by a decision of the Minister, no person or entity other than the Ministry may produce or distribute electricity and water except under a written licence from the Minister in the cases and on the conditions set by a Council of Ministers decision. Among the Ministry's powers under items (7) and (8) of Article (3) are preparing and concluding electricity and water connection contracts and preparing connection application forms, and setting connection fees and consumption tariff schedules in the various areas after Cabinet approval. Consumed quantities are measured by meters the Ministry provides or by the means it sees fit; the bill is issued on the reading or by estimation when the meter fails, and must be paid within the period the Ministry sets, under Article (5). The Ministry may cut the service after giving the consumer a sufficient grace period and a warning by registered letter in three cases: failure to pay the fees due on the bill, non-conformity of equipment, devices and internal installations with safety requirements, and erecting internal installations without a licence, under Article (6). The Electricity and Water Authority was established by Decree No. (98) of 2007 and reorganized by Decree No. (38) of 2024.
Telecommunications and Interconnection
The Telecommunications Law issued by Legislative Decree No. (48) of 2002 defines interconnection as the physical and logical linking of telecommunications networks used by the same telecommunications operator or another operator, to enable subscribers of one operator to communicate with subscribers of the same operator or of another operator or to obtain services provided by another operator. Among the powers of the Telecommunications Regulatory Authority under item (13) of Article (3) is encouraging, organizing and facilitating suitable access, interconnection and interoperability of services, including mandating public telecommunications operators to share the use of facilities and properties where necessary.
Article (24)(a), as replaced by Legislative Decree No. (18) of 2023, prohibits any person from operating a public telecommunications network or any telecommunications network using a telecommunications frequency, or providing a telecommunications service in the Kingdom, except after obtaining a licence or an exemption from the Authority under the Law, with exemption cases and conditions organized by a decision of the Authority; paragraph (b) prohibits connecting a licensed telecommunications network to any other network or to any unapproved devices without a permit granted under the terms of the relevant licence. If the operator decides to provide telecommunications services to others from its site, Article (26)(a) requires for the grant of any licence that the applicant be a legal person established in the Kingdom or a branch of a foreign company licensed to practise the activity in it under the Commercial Companies Law, and that the infrastructure and staff concerned with providing the services exist in the Kingdom in substance. The Authority alone may exempt from the substantial-presence condition in either of two cases: a substantial need for a telecommunications service that cannot effectively be provided except through infrastructure and staff located outside the Kingdom, provided the benefit of that service accrues directly to subscribers and users, as the Authority assesses from the obligations set out in the licence or otherwise; or breach by licensees of the obligations in paragraph (a) of Article (65), under paragraph (b) of Article (26).
May a foreign company own the data center land in Bahrain?
Yes. Non-Bahraini legal persons may own property in the areas and on the conditions set by a Council of Ministers decision under Legislative Decree No. (2) of 2001, and Council of Ministers decisions delimit the areas in accompanying maps replaced from time to time; Article Three of Decision No. (43) of 2003 allowed companies wholly owned by non-Bahrainis and licensed for industrial activities to own properties in the industrial zones to establish their projects, with the usufruct of zones governed by Legislative Decree No. (28) of 1999 subject to that law.
What is the effect of not registering the land purchase contract?
Registration is required of all disposals creating, establishing or transferring original or accessory in-rem property rights or effecting the lapse of any of them, of final court judgments establishing any of that, and of acknowledgments of waiver of the registration rank of accessory in-rem rights; if not registered, those rights do not arise, are not established, do not pass, do not change and do not lapse, neither between the parties nor against others, under Article (17) of the Real Estate Registration Law issued by Law No. (13) of 2013, and an unregistered disposal has no effect beyond personal obligations between the parties under Article (18).
Is there a maximum term for an industrial land lease?
Yes. An industrial zone land lease may not exceed fifty years unless otherwise agreed, under Article (15) of Legislative Decree No. (28) of 1999. Lease contracts must be notarized at the notarization office of the Ministry of Justice and Islamic Affairs, and the tenant alone bears the notarization fees.
What are the rules on assigning the lease and subletting?
In the industrial zones, assignment of the lease is allowed with the Ministry's approval while the assignor remains jointly liable with the assignee for prior financial obligations; subletting is allowed only with the Ministry's written approval; and neither takes effect against the Ministry or third parties except from notarization, under Article (21) of the industrial zones law.
Who supplies the data center with power and water?
The competent electricity and water ministry produces, develops, transmits, distributes and sells electrical power for all purposes, and extracts, produces, distills, desalinates, stores, delivers, distributes and sells water for drinking and for domestic, commercial and industrial uses under Article (2) of Legislative Decree No. (1) of 1996, and no one else may produce or distribute them except under a written licence from the Minister in the cases and on the conditions set by a Council of Ministers decision, apart from personal use. Connection is made under contracts prepared by the Ministry for fees and tariffs set after Cabinet approval.
In which cases may power or water be cut off from the site?
The Ministry may cut electricity or water or both only after giving the consumer a sufficient grace period and a warning by registered letter, in three cases: failure to pay the fees due on the bill, non-conformity of equipment, devices and internal installations with safety requirements, and erecting or creating internal installations without a licence from the Ministry, under Article (6) of Legislative Decree No. (1) of 1996.
Does a data center need a telecommunications licence?
Article (24) of the Telecommunications Law prohibits operating a public telecommunications network or a network using a telecommunications frequency or providing a telecommunications service without a licence or exemption from the Authority, and prohibits connecting a licensed network to another network or to unapproved devices without a permit. If the center decides to provide telecommunications services to others, the requirements of Article (26) apply, including that it be a legal person established in the Kingdom or a branch of a foreign company licensed to practise the activity there, with infrastructure and staff present in the Kingdom in substance. The Authority alone may exempt from the substantial-presence condition in the two cases of paragraph (b) of the same article.