Muqawala and Maintenance Works in Bahrain: Risk, Compensation and Notice Under the Civil Code

Bahrain's Civil Code (Legislative Decree No. 19 of 2001) regulates muqawala (contracting works) in arts 584 to 620.

Muqawala and maintenance works

Article 584 of the Civil Code defines muqawala as a contract under which one party undertakes to perform work for the other in return for consideration, without being subordinate to it or acting as its agent.

Maintenance has a specific provision in Article 607: where the muqawala requires the contractor to maintain a specific thing or to perform other recurring works during a fixed period, the muqawala ends on the expiry of that period.

The contractor's obligations

Article 589 requires the contractor to complete the work according to the terms of the contract and within the agreed period; where there are no terms or no agreed period, it must perform according to recognized practice and within the reasonable time the nature of the work requires, observing trade custom. It must also provide at its own expense the labor, tools and equipment needed, unless the agreement or trade custom provides otherwise.

Where work materials are supplied by the owner, Article 587 requires the contractor to keep them with the care of an ordinary person, to observe technical standards in using them, to account for them and to return what remains. If the materials become unfit for use because of its neglect or deficient technical competence, it must repay their value, with compensation where warranted.

Article 588 provides that if defects occur or appear during performance in materials supplied by the owner, or other factors arise that could obstruct performance in suitable conditions, the contractor must notify the owner immediately; if it neglects to notify, it is liable for every consequence of that neglect.

On the standard of obligation, Article 214 provides that a debtor required to keep a thing, manage it or observe caution in performing its obligation has performed if it exercises the care of an ordinary person even where the intended result is not achieved, unless the law or the agreement provides otherwise, and it remains liable in every case for its fraud or gross fault.

The owner's obligations

Article 594 provides that where performance requires the owner to make a specific contribution and it fails to do so in good time, the contractor may call on it to perform within a reasonable period it fixes; if the period lapses without performance, the contractor may seek termination of the contract, without prejudice to its right to compensation where warranted.

On consideration, Article 599 entitles the contractor to payment on delivery of the work unless the agreement or custom provides otherwise, and Article 600 allows the contractor, where the work consists of several parts or the consideration is fixed per unit, to be paid in proportion to the work completed after it has been inspected and accepted, provided the completed work is a distinct part or a section of sufficient importance to the work as a whole, unless otherwise agreed.

Under Article 602, rises or falls in the cost of the work have no effect on the extent of the obligations the contract creates, without prejudice to Article 130 on exceptional circumstances.

Ending the muqawala and stopping the work

The owner holds an important statutory power: Article 611 allows it to terminate the muqawala and stop performance of the work at any time before completion, provided it compensates the contractor for all expenses incurred, works completed and what it could have earned had it completed the work, and the court may reduce the compensation due for lost earnings where circumstances make reduction fair.

If performance of the work becomes impossible for a reason beyond either party's control, the muqawala ends under Article 608, and the contractor may claim from the owner what it spent and the pay due to it within the limits of the benefit that accrued to the owner. Article 145 provides that in a contract binding both sides, if performance of one party's obligation becomes impossible for an external cause beyond its control, that obligation and the corresponding obligations lapse and the contract is dissolved automatically; if the impossibility is partial, the creditor may, as the case requires, hold to the contract for what remains possible or ask for dissolution.

Allocating reciprocal risks

Under Article 592, if the thing is destroyed or damaged by a sudden accident or force majeure before delivery to the owner, the contractor may not claim the agreed consideration or repayment of its expenses, unless the owner at the time of destruction or damage was in default of its obligation to take delivery.

Under Article 593, where materials are supplied by the owner and the thing is destroyed or damaged before delivery by a sudden accident or force majeure, the owner may not claim their value from the contractor, unless the contractor was in default of its obligation to deliver the work and fails to prove the thing would have been destroyed had it delivered without default.

The parties may redraw this allocation by agreement: Article 218 permits agreeing that the debtor bears the consequences of force majeure or sudden accident, and Article 219 permits agreeing to exempt the debtor from any liability arising from non-performance of its contractual obligation or delay in performing it, except what arises from its fraud or gross fault.

Where the creditor's fault combines with the debtor's fault in causing the damage and neither fault absorbs the other, the court reduces the compensation by the part that corresponds to the creditor's fault (Article 217).

Compensation and the notice rules

The baseline of contractual liability is Article 216: where performance in kind is impossible or the debtor delays performance, it must compensate the damage caused to the creditor, unless it proves the non-performance or delay was due to an external cause beyond its control. Compensation is due only after notice to the debtor, unless the agreement or the law provides otherwise (Article 220). Notice is given by a registered letter with acknowledgment of receipt, without an envelope, or by an official document that takes the place of a warning, and it may also be given by any other agreed means (Article 221).

Article 222 dispenses with notice in defined cases, including an agreement that the debtor is in default simply on failing to perform when the term falls due, performance in kind becoming impossible or futile through the debtor's act, and the debtor's written declaration that it will not perform.

The court assesses compensation where it is not fixed in the contract or by text, and under Article 223 it covers the loss suffered and the gain missed, provided it is a natural result of the non-performance or delay; a debtor who committed no fraud or gross fault compensates only the damage that could ordinarily have been foreseen at the time of contracting.

Where the object of the obligation is not a sum of money, the parties may fix the compensation in advance, in the contract or in a later agreement (Article 225). Articles 226 and 227 discipline this: agreed compensation is not due if the debtor proves the creditor suffered no harm, the court may reduce it if the debtor proves it was grossly exaggerated or that the main obligation was partly performed, any contrary agreement is void, and where the damage exceeds the agreed compensation the creditor may not claim more unless it proves fraud or gross fault.

Frequently asked questions

What is muqawala, and what does the Civil Code say about maintenance works?

Muqawala is a contract under which one party undertakes to perform work for the other in return for consideration, without being subordinate to it or acting as its agent (Article 584). Where the muqawala requires the contractor to maintain a specific thing or to perform other recurring works during a fixed period, the muqawala ends when that period expires (Article 607).

Who bears the risk of destruction or damage of the thing before delivery to the owner?

If the thing is destroyed or damaged by a sudden accident or force majeure before delivery to the owner, the contractor may not claim the agreed consideration or repayment of its expenses, unless the owner was, at that time, in default of its obligation to take delivery (Article 592). Where the materials are supplied by the owner, the owner may not claim their value from the contractor, unless the contractor was then in default of its obligation to deliver the work and the contractor fails to prove that the thing would have been destroyed had it delivered without default (Article 593). The parties may agree that the debtor bears the consequences of force majeure or sudden accident (Article 218), and may agree to exempt the debtor from liability for non-performance or delay, except what arises from its fraud or gross fault (Article 219).

Can the owner end the muqawala and stop the work before it is completed?

Yes. The owner may end the muqawala and stop the work at any time before it is completed, provided it compensates the contractor for all expenses incurred, the works completed and what it could have earned had it completed the work, and the court may reduce the compensation for lost earnings where circumstances make the reduction fair (Article 611).

Is notice to the debtor required before claiming compensation?

As a rule, yes: compensation is due only after notice to the debtor, unless the agreement or the law provides otherwise (Article 220). Notice is given by a registered letter with acknowledgment of receipt, without an envelope, or by an official document that takes the place of a warning, or by any other agreed means (Article 221). Notice is not needed in the cases of Article 222, such as an agreement treating the debtor as in default on the due date alone, or the debtor's written declaration that it will not perform.