Under the Bahrain Civil Law (Decree-Law 19 of 2001), a works contract is a contract by which one party undertakes to do work for the other for a price, without being the other's subordinate or agent (Article 584).
Subcontracting and assigning the contract
The contractor may entrust all or part of the work to a subcontractor, unless the contract prevents it or the nature of the work makes the contractor's personal identity a matter of consideration (Article 604(a)). Subcontracting does not affect the main contractor's obligations to the owner, and the main contractor remains answerable to the owner for the subcontractor's work (Article 604(b)).
Neither contracting party may assign the contract without the other's consent, unless the contract provides otherwise (Article 603(a)). If the contract is assigned, the assignee takes the place of the assignor in its rights and obligations (Article 603(b)). The assignment does not bind third parties unless it was officially notified to the other contracting party or that party's consent has a certain date (Article 603(c)).
Grounds for ending the contract or replacing the contractor
If, during the work, the contractor performs defectively or contrary to the contract, the owner may warn the contractor by registered letter with acknowledgment of receipt, sent without an envelope, to correct the method of performance within a reasonable period set by the owner. If the period passes and the contractor has not returned to the correct or agreed method, the owner may ask the court to rescind the contract or to authorize the owner to entrust the work to another contractor at the first contractor's expense, where the nature of the work allows it (Article 590(a)). Rescission may be requested without a warning or a period if repairing the defect or breach is impossible (Article 590(b)). In all cases the judge may refuse rescission if the defect or breach does not greatly reduce the value of the work or its fitness for the intended use, without prejudice to compensation where due (Article 590(c)).
The owner may also ask for rescission without waiting for the delivery date if the contractor is so late in starting or finishing the work that it cannot be expected to perform properly within the agreed period, shows an intention not to perform, or does an act that makes performance impossible (Article 591).
If the owner fails in due time to perform an act that the work requires, the contractor may call on the owner to perform it within a reasonable period the contractor sets, and if the period passes the contractor may ask for rescission, without prejudice to compensation where due (Article 594). The contract ends if performance of the work becomes impossible for a reason neither party caused, and the contractor may then claim its expenses and the pay it is due, within the limit of the benefit that returned to the owner (Article 608). The owner may end the contract and stop the work at any time before completion, but must compensate the contractor for all expenses incurred, work done and the profit it could have earned by completing the work (Article 611(a)). The court may reduce the compensation for lost profit if the circumstances make that fair (Article 611(b)).
Handover, defects and stage payments
When the contractor has completed the work and placed it at the owner's disposal, the owner must take delivery as soon as possible according to usual dealings. If the owner refuses without a lawful reason after being called on by formal notice, the work is considered delivered (Article 595).
The owner may refuse delivery if the defect or deviation from the agreed terms is so serious that the work no longer serves its intended purpose, subject to Article 614 (Article 596(a)). If the defect or deviation is less serious, the owner may only ask for a price reduction in proportion to its importance, or require the contractor to repair it within a reasonable period the owner sets, if repair is possible and does not involve excessive cost (Article 596(b)). The contractor may also repair within a reasonable period if that is possible and causes the owner no harm of value (Article 596(c)). The owner may not rely on these rights if the owner caused the defect, whether by orders contrary to the contractor's opinion or in any other way (Article 597).
Once the work is delivered, the contractor is no longer liable for an apparent defect or breach of the contract terms, subject to Article 615 (Article 598(a)). If a defect or breach is hidden and the owner finds it after delivery, the owner must notify the contractor promptly, otherwise the owner is considered to have accepted the work. If the contractor is notified, Article 596 applies (Article 598(b)).
Unless the agreement or custom provides otherwise, the contractor is entitled to the price when the work is delivered (Article 599). Where the work consists of several parts or the price is set per unit, the contractor may collect part of the price in proportion to the work done after the owner has inspected and accepted it, provided that the completed work is a distinct part or a section of sufficient importance to the work as a whole, unless otherwise agreed (Article 600(a)). A payment is presumed to mean that the work it paid for was inspected and accepted, unless it is proved that the payment was on account or custom provides otherwise (Article 600(b)). If the price was not fixed in advance, it is set by reference to the value of the work and the contractor's expenses (Article 601).
Estimates, lump sums and the building guarantee
Where the contract is based on an estimate and performance proves to require a grave excess over it, the contractor must promptly notify the owner and state the increase in price this entails, otherwise the contractor loses the right to claim the increase. In that case the owner may withdraw from the contract and stop performance, provided this is done without delay and the contractor is paid the value of the work done, assessed under the contract terms, without compensation for the profit it could have earned (Article 612). Where the price is a lump sum based on a design agreed with the owner, the contractor may not claim any increase for a change or addition to the design, unless it results from the owner's act or was authorized by the owner (Article 613).
Where a building or installation on land owned by the owner has defects as serious as Article 596(a) describes and removing it would cause grave damage, the owner may only ask for a price reduction or require repair under Article 596(b), without prejudice to compensation where due (Article 614).
The contractor and the engineer guarantee, for ten years from completion, any collapse or total or partial defect in the buildings or fixed installations they built, subject to the following articles. If the parties intended the building or installation to last less than ten years, the guarantee runs for the intended period. The guarantee covers collapse even if it arises from a defect in the land itself or the owner permitted the defective construction, and it covers defects that threaten the strength and safety of the building or installation (Article 615). Guarantee claims against the engineer or the contractor are not heard after three years from the collapse or the discovery of the defect (Article 619). Any term exempting the engineer or the contractor from the guarantee, or limiting it, is void (Article 620).
The contractor is liable only for defects in execution, not for defects arising from an error in the design, unless those defects are apparent, but is liable for design defects if the engineer who made the design is its subordinate (Article 617). An engineer whose work was limited to the design, or part of it, is liable for defects arising from the design but not from the method of execution, and an engineer entrusted by the owner with supervising the execution, or part of it, is also liable for defects arising from the method of execution that the engineer supervised (Article 616). Where the engineer and the contractor are both liable for a defect, they are jointly liable (Article 618).
Materials and custody
Where the owner supplies the materials, the contractor must care for them with the care of a reasonable person, follow technical rules in using them, account to the owner for them and return what remains (Article 587(a)). If the materials, or some of them, become unusable through the contractor's negligence or technical shortcoming, the contractor must return their value to the owner, with compensation where due (Article 587(b)). If defects appear in the materials the owner supplied, or other factors arise that would hinder performance under suitable conditions, the contractor must promptly notify the owner, and if it neglects to do so it is liable for all the results of that neglect (Article 588). Materials are considered supplied by the owner if the owner has paid their value or advanced a sum on account that includes it (Article 593(b)).
If the thing perishes or is damaged by sudden accident or force majeure before delivery to the owner, the contractor may not claim the agreed price or the refund of its expenses, unless the owner was in breach of the duty to take delivery at the time of the loss or damage (Article 592). Where the materials were supplied by the owner and the thing perishes or is damaged before delivery by sudden accident or force majeure, the owner may not claim their value from the contractor, unless the contractor was in breach of its duty to deliver at that time and it is not proved that the thing would have been damaged even if the contractor had delivered without breach (Article 593(a)).
Direct claims and priority over sums due
A subcontractor and the workers employed for the main contractor on the work may claim directly from the owner what is due to them from the main contractor, within the amount the main contractor is owed by the owner when the suit is filed (Article 605(a)). The subcontractor and the workers named in Article 605 collect their rights with priority over the sums due to the main contractor or to the subcontractor, and when they compete they share in proportion to each one's debt (Article 606).