Testing, Receipt, Guarantees and Final Account in Bahrain Infrastructure Projects

The Civil Code (Decree-Law No. 19 of 2001) governs receipt of the work, payment and guarantees in contracts for work. The owner's right to refuse receipt depends on how serious the defect is, receipt ends liability for apparent defects, and a separate guarantee covers buildings and fixed structures.

Refusing receipt of defective work

The owner may refuse to receive the work where a defect or breach of the agreed terms is so serious that the work no longer serves its intended purpose, subject to Article 614 (Article 596(a)). If the defect or breach is less serious, the owner may only ask for a proportionate reduction of the price, or require the contractor to repair within a reasonable period the owner sets, where repair is possible and does not involve excessive cost (Article 596(b)). In every case the contractor may repair within a reasonable time, where this is possible and causes the owner no damage of value (Article 596(c)). The owner cannot rely on these rights if the owner caused the defect, whether by orders against the contractor's opinion or in any other way (Article 597). Where a building or structure on the owner's land has defects of the gravity described in Article 596(a) and removing it would cause grave damage, the owner may only ask for a price reduction or for repair under Article 596(b), without prejudice to compensation where due (Article 614).

Receipt and hidden defects

Once the work is received, the contractor's liability for defects or breaches of the contract that were apparent in it ends, subject to Article 615 (Article 598(a)). If the defects or breach were hidden and the owner discovers them after receipt, the owner must promptly notify the contractor, or is treated as having accepted the work; once the contractor is notified, Article 596 applies (Article 598(b)). The contractor's price falls due on receipt of the work, unless agreement or custom provides otherwise (Article 599).

Payment by stage

Where the work consists of several parts, or the price is set per unit, the contractor may collect the part of the price matching the work done after inspection and acceptance, provided that the completed work is a distinct part or a section of sufficient importance to the work as a whole, unless the parties agreed otherwise. What has been paid for is presumed to have been inspected and accepted, unless it is proved that payment was on account or that custom provides otherwise (Article 600).

The ten year guarantee for buildings and fixed structures

The contractor and the engineer guarantee any collapse or total or partial defect in buildings they erected or fixed structures they built, for ten years from completion of the building or structure, subject to the following articles. If the parties intended the building or structure to last less than ten years, the guarantee runs for the intended period. The guarantee covers collapse even if it comes from a defect in the land itself or the owner approved the defective building or structure, and it covers defects that appear and threaten the strength and safety of the building or structure (Article 615). Guarantee claims against the engineer or the contractor are not heard once three years have passed from the collapse or the discovery of the defect (Article 619). Any term exempting the engineer or the contractor from the guarantee, or limiting it, is void (Article 620).

Who answers for design, supervision and execution

An engineer whose work is limited to preparing the design, or part of it, answers for defects arising from the design, not for defects arising from the method of execution; if the owner also entrusted the engineer with supervising execution, or part of it, the engineer also answers for defects arising from the execution supervised (Article 616). The contractor answers only for defects in execution, not for defects from an error in the design, unless the defects are apparent; the contractor does answer for design defects where the engineer who prepared the design works for the contractor (Article 617). Where the engineer and the contractor are both responsible for a defect, they are jointly liable (Article 618).

Frequently asked questions

When may the owner refuse to receive the work?

When a defect or breach of the agreed terms is so serious that the work no longer serves its intended purpose, subject to Article 614; for a less serious defect the owner may only ask for a price reduction or repair within a reasonable period (Article 596).

What happens to apparent defects once the work is received?

The contractor's liability for them ends, subject to Article 615. For hidden defects found after receipt, the owner must notify the contractor promptly or is treated as having accepted the work (Article 598).

How long does the guarantee for buildings and fixed structures last?

Ten years from completion, or the shorter period the parties intended the building or structure to last (Article 615). Guarantee claims are not heard after three years from the collapse or the discovery of the defect (Article 619).

Can a contract exclude the contractor's or the engineer's guarantee?

No. Any term exempting the engineer or the contractor from the guarantee, or limiting it, is void (Article 620).