In a business-to-business supply relationship under Egyptian law, the moment that decides most disputes is not the signature; it is the delivery. Whether the goods conformed, whether the buyer inspected them in time, what was written on the delivery note and what happened to the invoice afterwards will usually matter more than any recital. Egyptian law supplies a detailed set of default rules for delivery, inspection, acceptance and payment, and most of them yield to what the parties write down. This guide walks through the delivery and acceptance file for a commercial supply contract: the contract hierarchy, the delivery event and its evidence, inspection and acceptance, defect notices and cure, the payment trigger, and what to put in the review file. It does not cover construction certification, transport conventions or consumer sales.
The contract hierarchy: specification, purchase order and incorporated terms
A supply relationship usually lives in three documents: a master or frame contract, a technical specification, and the purchase orders placed under them. Disputes about acceptance are lost when the acceptance protocol exists only in a purchase order that contradicts the master contract, or only in a specification nobody signed. The hierarchy should be fixed in writing: which document prevails, how a purchase order is accepted, and where the inspection and acceptance procedure sits.
The delivery event, place, record and risk
The Civil Code defines what delivery means. Under Article 435, delivery happens by placing the goods at the buyer's disposal so that he can possess and use them without hindrance, even without physical taking, provided the seller has informed him; and it can happen by mere agreement where the buyer already holds the goods. Under Article 436, where the goods must be shipped to the buyer, delivery is only complete when they arrive, unless agreed otherwise. Article 463 adds that, absent agreement or custom, the buyer must collect the goods where they are at the time of sale and remove them without delay.
Risk follows delivery. Under Article 437, if the goods perish before delivery for a cause not attributable to the seller, the sale is rescinded and the buyer recovers the price, unless the buyer had already been formally summoned to take delivery. Because so much turns on when and where delivery legally happened, the delivery record is a legal document, not an administrative one: a dated delivery note naming the goods, quantities and apparent condition, signed by a person whose authority to receive is established, is the piece of paper the dispute will turn on.
Inspection and acceptance
Egyptian law puts the inspection duty on the buyer, and it has teeth. Under Article 449 of the Civil Code, a buyer who takes delivery must verify the condition of the goods as soon as he is able, in the manner customary in the trade; if he discovers a defect the seller warrants, he must notify the seller within a reasonable time, failing which he is deemed to have accepted the goods. Where the defect is one that ordinary inspection cannot reveal, he must notify as soon as it appears, failing which he is deemed to have accepted the goods with the defect.
The contract should convert this default into a procedure: a defined inspection window in days, the tests or counts that will be run, who signs the acceptance, and what partial acceptance means for a partial delivery. Acceptance should be written and qualified: an acceptance note that lists reservations is worth far more than silence, and under the default rule silence after the inspection window is acceptance. Rejection equally needs form: a written rejection notice, within the contractual or reasonable time, identifying the non-conformity and stating whether the buyer requires replacement, repair or refusal of the lot.
Defect notices, cure and evidence preservation
Two statutory clocks frame every defect discussion. Under Article 452, the defect warranty claim lapses one year from delivery even if the buyer discovers the defect later, unless the seller has accepted a longer warranty; and the seller cannot rely on that lapse if he fraudulently concealed the defect. Under Article 455, where the seller warranted the goods' fitness to work for a defined period and a malfunction appears, the buyer must notify within one month of its appearance and file suit within six months of the notice, unless agreed otherwise.
Evidence preservation is the unglamorous half of acceptance. When a defect appears, the buyer's file should hold the delivery note, the inspection record, dated photographs, retained samples where the goods allow it, the notice to the seller with proof of dispatch, and the seller's response.
The payment trigger and withheld sums
The default rule ties payment to delivery: under Articles 456 and 457, the price falls due at the place and time of delivery unless agreement or custom provides otherwise. Supply contracts usually replace this with an invoice-and-days mechanism, and that mechanism should be wired to acceptance rather than to arrival: the invoice clock should start from written acceptance, with a defined outside date by which an invoice is deemed payable if the buyer neither accepts nor rejects. Without that outside date, a silent buyer can hold both the goods and the price.
When the parties disagree over withheld sums, the drafting decides whether the buyer may withhold the whole price against a disputed lot or only the disputed proportion. Article 461 adds a further seller protection in sales of movables: where a time is fixed for payment and taking delivery, the sale is rescinded without the need for a formal notice if the price is not paid when due, at the seller's election, unless agreed otherwise. Buyers should know that this default exists before relying on a grace-period habit.
Mandatory rules, default rules and the review file
Most of the rules above are defaults that yield to the contract, which is precisely why the contract should speak. Article 453 lets the parties increase, reduce or exclude the defect warranty, but a clause excluding or reducing it is void where the seller fraudulently concealed the defect, and the same fraud exception protects the one-year limitation in Article 452. The review file for a supply relationship should therefore contain: the signed master terms with their hierarchy clause, the incorporated specification, the inspection and acceptance procedure with its windows, the delivery-note form and the named receiving authority, the notice addresses and methods, the warranty terms against Articles 452 and 455, and the payment trigger with its outside date.
FAQ
When does delivery legally happen in an Egyptian supply sale?
Under Article 435 of the Civil Code, when the goods are placed at the buyer's disposal so he can possess and use them without hindrance and he has been informed, even without physical taking. Where the goods must be shipped to the buyer, Article 436 makes delivery complete only on arrival, unless agreed otherwise.
Is the buyer really deemed to accept if he stays silent?
Yes. Under Article 449, a buyer who does not inspect as soon as he is able, or who fails to notify a discovered defect within a reasonable time, is deemed to have accepted the goods. The same applies to hidden defects not notified as soon as they appear.
How long do I have to claim for a defect?
Under Article 452, the defect warranty claim lapses one year from delivery, even if the defect is discovered later, unless the seller accepted a longer warranty. Fraudulent concealment by the seller defeats that limitation.
We agreed the seller warrants the machines will work for two years. What clocks apply?
Under Article 455, you must notify a malfunction within one month of its appearance and file suit within six months of that notice, unless the contract provides otherwise. The contract should be checked so its own procedure does not quietly consume these windows.
When is the price due if the contract says nothing?
Under Articles 456 and 457, at the place and time of delivery, unless agreement or custom provides otherwise. Between merchants, Article 93 of the Commercial Law sets delivery on conclusion of the contract where no time is agreed, unless the nature of the goods or custom sets another time.
Do these rules apply to construction works or carriage of goods?
No. Construction certification, the transport conventions and consumer sales follow their own rules. This guide covers business-to-business supply of goods between merchants.