Anyone planning a plant, resort, port or warehouse in Qatar should treat the environmental review as the first step, not the last. Decree Law No. 30 of 2002, which issued the Environment Protection Law, puts an environmental impact assessment in front of the licence and bars operation until the licence exists.
The licence rule
Under Article 13, licensing bodies may not issue licences for the projects that the Executive Regulation designates unless an environmental impact assessment study has been submitted and the Council, meaning the Supreme Council for Environment and Natural Reserves, has approved its results. This applies without prejudice to the other conditions set by the laws in force, so the environmental step does not replace the other licences a project needs. The same article bars operating the project or facility before it has obtained the required licence, complete with the study and the Council's approval. Expansions and renewals of existing projects are subject to the same assessment procedures.
Which projects, and at what stage
Under Article 11 the Council sets the criteria, specifications and rules for assessing environmental impact. It identifies the categories of public and private development projects that by their nature may cause environmental harm, and the areas and sites of environmental importance. The Executive Regulation sets the assessment procedures, the conditions for granting the environmental permit or the operating permit, and the cases where a permit is suspended or cancelled. Under Article 12, development plans and projects of every type and location, including industrial, agricultural and urban projects, are presented to the Council at the planning stage and before execution, so that it can review and assess them.
Review time and objections
Under Article 14, the licensing body sends a copy of the study to the Secretariat General of the Council, which gives its opinion and refers the study to the Council for a decision. The Secretariat General must give the licensing bodies the Council's decision within thirty days at most from the date the study arrives complete. If that period passes without a reply from the Secretariat General, this counts as approval of the study. A person affected by a Council decision rejecting the study may file a grievance under the rules, procedures and deadlines that the Executive Regulation sets.
What the assessment is
The Law defines environmental impact assessment as the study of environmental feasibility carried out before licensing projects whose establishment or activity may affect the environment. Its purpose is to identify the likely environmental effects and the measures that prevent, remove or reduce negative effects or increase the project's positive effects.
Hypothetical example (not a real case)
Harbour Light Marine plans a small marina with a fuel dock and already holds its building permit. If a project of this kind is among those the Executive Regulation designates, the licensing body cannot issue the licence until the study has been submitted and the Council has approved its results. The company then sends the licensing body the study, the licensing body forwards a copy to the Secretariat General, and the company does not fuel a single boat before the licence is in its hands.
Frequently asked questions
Can a licence be issued before the environmental approval?
Not for projects that the Executive Regulation designates. Article 13 allows the licence only after the study is submitted and the Council has approved its results.
Does the Law say anything about sensitive areas?
Yes. Under Article 11 the Council identifies the areas and sites of environmental importance according to environmental protection criteria.
Can a rejection be challenged?
Yes. Article 14 lets the person concerned file a grievance against a Council decision of rejection, under the rules, procedures and deadlines set by the Executive Regulation.
Do operators have to keep records once the project is running?
Yes. Under Article 16, project owners must keep a register showing the effect of the facility's activity on the environment. The Executive Regulation sets the model for the register and the data entered in it. The Secretariat General follows the register data, and may take samples and run tests. If it finds violations, it notifies the competent administrative body, which directs the owner to correct them quickly. If the owner does not do so within sixty days, the Council, on the Secretariat General's recommendation, may take the steps needed to stop the violating activity and claim appropriate compensation.
Is there an extra rule for a project on the coast?
Article 57 makes it a condition for licensing a project, facility or shop on or near the seashore that results in the discharge of polluting materials in breach of the Law and its implementing decisions that the applicant carries out environmental impact studies and provides the means to treat waste.
What is the penalty for operating before the licence?
Article 68 punishes a breach of Article 13 paragraph 2, which is operating before the licence with the study and the Council's approval, with a fine of not less than 5,000 and not more than 50,000 riyals. Article 66 keeps in place any heavier penalty that the Penal Code or another law provides, so the fine is not always the only exposure. The fine range applies to the articles that the Law's penalties chapter lists with their penalties, and Article 68 is one of them.
What happens on a repeat offence?
Article 66 doubles the penalty in case of repeat for a person who violates the articles that the Law's penalties chapter lists with their penalties, without prejudice to any heavier penalty under the Penal Code or another law. Under Article 72, a repeat offender is anyone who commits a crime similar to one already punished, before five years have passed from the end of serving the penalty or its lapse by prescription.