Scope and Competent Authority
This article covers the environmental permits a local or foreign company needs to build and operate a project in Saudi Arabia, and what follows when the project changes after the permit is issued. The framework rests on the Environment Law issued by Royal Decree No. M/165 dated 19/11/1441H and the Implementing Regulation for Environmental Permits for the Construction and Operation of Activities. The Law provides that no person may carry on an environmental activity or an activity with an environmental effect except after obtaining a permit or licence as the regulations specify (Article 3 of the Law). The Regulation applies to all persons who own or operate any activity with an environmental effect, new or existing, within the Kingdom, including construction, operation, modification, addition, expansion and closure (Article 2 of the Regulation). An activity means any project, industrial, commercial or service facility, or works expected to have environmental effects (Article 1 of the Regulation). The permit is issued by the National Center for Environmental Compliance, which receives and reviews classification forms and impact assessment studies, issues and renews environmental permits and licences, collects the set fee and monitors compliance with permit conditions (Article 3 of the Regulation).
Classifying the Activity by Environmental Impact
Activities fall into three categories according to their environmental effects, and the category decides whether an impact assessment study is needed (Article 4, paragraph 1 of the Regulation). The Center reviews the classification by looking at the type and size of the activity, the energy used, the depletion of natural resources, land use, the sensitive receptors around it, and the nature, extent, duration, reversibility, likelihood and level of the effects (Article 4, paragraph 2 of the Regulation). Category 1 covers activities expected to have minor effects that do not go beyond the site. Category 2 covers moderate effects that can be limited and controlled and do not extend much beyond the site. Category 3 covers activities expected to have serious environmental, social and economic effects that may go beyond the site (Article 4, paragraph 4 of the Regulation). The head of the Center issues updated guidance lists for classifying activities. They are guidance, so the Center itself decides the category after reviewing the form (Article 4, paragraph 3 of the Regulation).
The Environmental Classification Form and the Decision Period
The applicant completes the environmental classification form in the model in Annex 1 and submits it to the Center with the documents the Center specifies (Article 5, paragraph 1 of the Regulation). After the fee is paid, the Center issues its classification decision within 10 working days of receiving the form. The decision may set the category or ask for corrected information or missing items, in which case the final decision comes within 10 working days of receiving the complete information or the amended form (Article 5, paragraph 2 of the Regulation). The Center may extend the period by up to 10 more days if the activity is not previously classified in its lists, and it notifies the applicant of the result (Article 5, paragraph 3 of the Regulation). If the applicant shows modifications, measures or improvements that reduce the environmental effect, it may ask for the activity to be reclassified (Article 5, paragraph 4 of the Regulation).
The Environmental Construction Permit
All persons must obtain an environmental construction permit from the Center before starting any construction works or any change in the activity, and the applicant submits the classification form with the request (Article 6, Second, paragraphs 1 and 3 of the Regulation). The Center reviews the request and decides once the requirements for the category in Table 1 are met, and it may amend the requirements as needed (Article 6, Second, paragraph 5 of the Regulation). For Category 1 the requirement is the Center's approval of the environmental management plan and of the environmental rehabilitation plan for activities specified under the rehabilitation regulation, both prepared by a service provider licensed by the Center, after the fee is paid. For Category 2 it is approval of the impact assessment study under Article 7, and for Category 3 approval of the study under Article 8 (Table 1 of the Regulation). The permit states its validity and any conditions the Center sets, and the holder must comply with them (Article 6, First, paragraphs 3 and 4 of the Regulation). A construction permit is valid for three years. The Center may extend it by two additional years for large projects that need long periods to complete design and financing, and the extension request must then be included in the impact assessment study (Article 6, Second, paragraph 8 of the Regulation). The Center may refuse the permit, but the refusal must state reasons (Article 6, Second, paragraph 10 of the Regulation).
Impact Assessment Study for Category 2
This provision applies when the Center asks the applicant to prepare a Category 2 study. The study is prepared through a service provider licensed by the Center in the structure and information model in Annex 2 and submitted to the Center (Article 7, paragraphs 1, 2 and 3 of the Regulation). After the fee is paid, the Center decides within 30 working days of receiving the study. It may approve the study, ask for corrected information or missing items, in which case it issues its final decision within 30 working days of receiving the complete information or the amended study, or ask for a Category 3 study if it finds that necessary, taking into account the period already used and the fee difference (Article 7, paragraph 4 of the Regulation). When the Center approves the study and issues the construction permit, the applicant undertakes to carry out the study's findings and recommendations (Article 7, paragraph 5 of the Regulation).
Impact Assessment Study for Category 3
A Category 3 assessment has two parts: a scoping report and then the impact assessment study itself (Article 8, paragraph 2 of the Regulation). The applicant prepares the scoping report through a licensed service provider in the model in Annex 3 and submits it. The Center issues its approval or comments within 15 working days of receiving the report and may extend that by up to 10 more working days. If it issues neither approval nor comments within the extension, the applicant may treat the report as approved and follow it when preparing the study (Article 8, Second, First, paragraphs 1, 2 and 3 of the Regulation). The applicant then prepares the study in the model in Annex 4 in line with the Center's comments on the scoping report. The Center decides within 60 working days of receiving it, and if it asks for corrections it issues its final decision within 60 working days of receiving the amended study (Article 8, Second, paragraphs 1 and 2 of the Regulation). On approval and issue of the permit the applicant undertakes to implement the findings and recommendations (Article 8, Second, paragraph 3 of the Regulation). The periods run in working days from the date the Center actually receives the submission, so an investor should build the project schedule on the possibility of a second review round.
Sensitive Areas and Sensitive Receptors
Activities located within sensitive environmental areas or sensitive receptors, or within 500 metres of them, must carry out a detailed impact assessment study (Article 6, Second, paragraph 6 of the Regulation). Sensitive environmental areas include protected areas, parks, forests, wetlands, areas important for birds, mangroves, sites of natural scenery, water catchments and flows, sea shores, waterways and aquifers, and any area designated by the State, the Ministry or the national environmental centers. Sensitive receptors include environmental components, living organisms, archaeological, cultural and religious sites and community groups, for example endangered species, hospitals, care homes for the elderly, schools and residential complexes (Article 1 of the Regulation). The Center may also ask for an impact assessment study contrary to the classification conditions, provided the request states reasons (Article 6, Second, paragraph 7 of the Regulation).
The Environmental Operating Permit
All persons must obtain an environmental operating permit from the Center before operating or carrying on any activity. The Center issues it once all the conditions it sets are met, including the conditions and requirements of the construction permit (Article 6, Third, paragraphs 1 and 4 of the Regulation). Renewing the permit for Categories 2 and 3 requires an environmental audit study under the regulation on environmental inspection and audit every three years (Article 6, Third, paragraph 6 of the Regulation). The Center sets the permit's validity at not less than three years and not more than six years, taking into account the size of the activity, the complexity of its operations and operation and maintenance considerations (Article 6, Third, paragraph 7 of the Regulation). The Center collects the fee for issuing and renewing the permit and may refuse it with stated reasons (Article 6, Third, paragraphs 8 and 9 of the Regulation). It may include closure rules and conditions for the activity among the conditions of the operating permit (Article 9, paragraph 9 of the Regulation).
Changing the Project After the Permit
A major change under the Regulation is any expansion or change in the design, operation or nature of an existing activity that is likely to have a negative effect on the environment (Article 1 of the Regulation). Three provisions follow from it. First, a construction permit is needed before any construction works or change in the activity (Article 6, Second, paragraph 1 of the Regulation). Second, a new operating permit is needed before any modification to the type or size of the activity (Article 6, Third, paragraph 2 of the Regulation). Third, the Center may suspend the construction and operating permit if major modifications are made to the activity after the permit is obtained, until the necessary correction is made, with penalties applied to the violations committed (Article 9, paragraph 6 of the Regulation). An activity may not be split into phases with studies submitted in stages in a way that prevents correct classification or verification of its negative effects. Otherwise the Center may refuse the study or cancel an earlier approval even if parts of the activity obtained the construction permit (Article 9, paragraph 2 of the Regulation). The permit holder must start construction works before the construction permit expires. If it expires, a new construction permit and an updated impact assessment study are needed for Categories 2 and 3, and the classification form must be filled in again for Category 1. The fee paid is not refundable and the Center charges a new fee when the request is repeated (Article 9, paragraphs 4 and 5 of the Regulation).
General Provisions That Matter to an Investor
Persons must take the impact assessment into account in feasibility studies and preliminary designs (Article 9, paragraph 1 of the Regulation). Reports, documents and studies on the activity must be submitted in Arabic, and the Center may accept all or part of them in English (Article 9, paragraph 8 of the Regulation). Impact assessment studies and the analyses, tests and measurements in them must come from a service provider licensed by the Center (Article 3 of the Regulation). The Center may summon the applicant to present the study (Article 9, paragraph 3 of the Regulation). The permit holder is responsible for, and must remedy, any environmental effect that appears during the activity and was not mentioned in the studies submitted or was based on wrong information (Article 9, paragraph 7 of the Regulation). Under the Law, the permit holder and licensee must comply with the Law, the regulations, the permit conditions and the relevant decisions of the competent authority (Article 4 of the Law).
Objecting to the Center's Decisions
The applicant may object in writing before the Center to its decisions on environmental permits within 15 working days of notification, and objections received after that period are not accepted. The Center must decide on the objection within 30 working days of receiving it (Article 10 of the Regulation). The period is short, so the investor should track the date of notification and prepare the written objection quickly.
Violations and Penalties
Violations of the Regulation are recorded and penalties imposed under Schedule 2 referred to in the Regulation, according to the implementing regulation on recording violations and imposing penalties under the Environment Law (Article 11 of the Regulation). Under the Regulation a violation is grave if it consists of acts listed in Article 35 of the Law, leads to environmental degradation, or damages sensitive receptors or sensitive environmental areas. The fine for grave violations is assessed by a committee according to the degree of harm, the size of the damaged site, the type of receptors and the economic and social effects (Article 11 of the Regulation). Under the Law, whoever violates the Law or the regulations is punished by one or more of the following: a fine not exceeding SAR 20,000,000, suspension of the licence or permit for not more than six months, or cancellation of the licence or permit, without prejudice to a heavier penalty in another law (Article 38, paragraph 1 of the Law). The competent authority imposes fines not exceeding SAR 100,000 under the violation classification schedules, committees hear the other penalties and objections to fines, and committee decisions may be challenged before the Administrative Court (Article 39, paragraphs 1, 2 and 4 of the Law).
Practical Risks for a Foreign Investor
The first risk is starting any construction work or modification before the construction permit is issued, because the permit is a condition that precedes the start. The second is planning the schedule on the minimum review time, when a decision may be followed by a correction request and then a final decision with a new period. The third is treating the guidance classification lists as final, when the Center decides the category. The fourth is splitting the project into phases with separate studies, which lets the Center refuse the study or cancel its earlier approval. The fifth is letting the construction permit expire before works start, which requires an updated study and a new fee. The sixth is changing the type or size of the activity after operation starts without a new operating permit. The seventh is relying on inaccurate information in the study, because the permit holder bears responsibility for effects not mentioned or based on wrong information. A foreign company should make sure the studies are prepared in Arabic by a licensed service provider.
Hypothetical Example
This is a hypothetical example, not a real case. A foreign company and a local partner plan to build a factory on land 400 metres from a protected area. The company submits the classification form and finds that the site is within 500 metres of a sensitive area, so it must carry out a detailed impact assessment study through a licensed service provider and submit it in Arabic. After the Center approves, the construction permit is issued for three years and the company undertakes to carry out the study's findings. Works begin before the period ends. After two years the company wants to increase the factory's production capacity significantly. It does not start the work before presenting the change to the Center, and it applies for a new operating permit before changing the size of the activity. Had it carried out the increase first, its permit could have been suspended and it would have been exposed to penalties.
Frequently Asked Questions
May construction start before the environmental construction permit is issued
No. All persons must obtain an environmental construction permit from the Center before starting any construction works or any change in the activity (Article 6, Second, paragraph 1 of the Regulation).
How long does the Center take to decide on the classification form
10 working days from receiving the form after the fee is paid. The Center may extend that by up to 10 more days if the activity is not previously classified in its lists. If it asks for corrections or missing items, its final decision comes within 10 working days of receiving the information (Article 5, paragraphs 2 and 3 of the Regulation).
When is a detailed impact assessment study required
For activities within sensitive environmental areas or sensitive receptors, or no more than 500 metres from them (Article 6, Second, paragraph 6 of the Regulation). A study is also required for Categories 2 and 3 according to the Center's decision, and the Center may ask for a study contrary to the classification by a reasoned request (Article 6, Second, paragraphs 5 and 7 of the Regulation).
How long is a construction permit valid and can it be extended
Three years. The Center may extend it by two additional years for large projects that need long periods to complete design and financing, and the extension request must be included in the impact assessment study (Article 6, Second, paragraph 8 of the Regulation).
Is a new permit needed when the type or size of the activity is modified
Yes. A new environmental operating permit must be obtained before any modification to the type or size of the activity (Article 6, Third, paragraph 2 of the Regulation).
How long is the period to object to the Center's decision on a permit
15 working days from notification, in writing before the Center. Objections after that period are not accepted, and the Center must decide within 30 working days of receiving the objection (Article 10 of the Regulation).
What are the penalties for violating the Law and the regulations
A fine not exceeding SAR 20,000,000, suspension of the licence or permit for not more than six months, or its cancellation, without prejudice to a heavier penalty in another law. Committee decisions may be challenged before the Administrative Court (Article 38, paragraph 1 and Article 39, paragraph 4 of the Law).