Oman

Ending a Contract, Proving Notice and Settling the Effects in Oman

A party in Oman wants to leave a contract, and the other side says it is still bound. The Civil Transactions Law, Royal Decree No. 29 of 2013, sets the ways a contract can end, the notice that goes with them, and what each side gets back. A party chooses the route according to why it wants out.

Scope and limits

Contracts governed by sector laws, employment, agency, lease and construction rules that differ from the general part, arbitration clauses, evidence rules, tax, insolvency and later amendments are separate matters. Whether a contract has ended and what each side owes is for the court to decide on the facts.

The binding force of a contract

A valid and effective contract takes effect on its subject and its consideration once it is made, and each party must perform what it imposes, unless the law provides otherwise (article 155). If the contract is valid and binding, neither party may terminate or modify it except by mutual agreement or by judgment (article 167). A party therefore has no right to leave on its own decision unless the contract or the law gives it one.

Termination by mutual release

A release between the parties is termination, and for third parties it is a new contract (article 168). It is made by offer and acceptance in the session or by exchange, and on condition that the subject of the contract exists and is in the hand of the contracting party at the time of the release. If part of it has perished, been damaged or been disposed of to another, the release is allowed for the rest in proportion to its share of the consideration (article 169).

A clause for automatic termination

The parties may agree that the contract is treated as terminated of its own accord, without a court judgment, if the obligations arising from it are not performed. This agreement does not remove the need for notice unless the parties expressly agree to waive it (article 170).

Termination by the court for non-performance

In a contract binding on both sides, if one party does not perform what the contract requires, the other may, after giving notice to the debtor, demand performance or termination (article 171, paragraph 1). The court may order performance at once or allow a set period, and it may rule termination while the refusal continues. In all cases it awards compensation if there is ground for it (article 171, paragraph 2).

Impossibility from force majeure

In a contract binding on both sides, if force majeure makes performance impossible, the matching obligation lapses and the contract terminates of its own accord (article 172, paragraph 1). If the impossibility is partial, the part matching what became impossible lapses, and the same applies to temporary impossibility in continuing contracts. In these two cases the creditor may terminate the contract on condition of giving notice to the debtor (article 172, paragraph 2).

Notice and its proof

Compensation is due only after notice to the debtor unless a provision says otherwise (article 265). No notice is needed where performance in kind has become impossible or useless through the debtor's act, where the object is compensation arising from an unlawful act, where the object is the return of a thing the debtor knows to be stolen or received without right, or where the debtor states in writing that he will not perform (article 266). Notice also comes before a demand for performance or termination (article 171) and stays necessary under an automatic termination clause unless expressly waived (article 170). The text of these articles sets no form for notice, so a party should keep a record of how and when it was given. Proof is a matter for the court.

Effects of termination

When a contract is terminated or terminates, the parties are returned to the state they were in before the contract, with the rights that follow, and if that is impossible the court awards compensation (article 173). Where performance in kind becomes impossible, or the debtor is late, he is ordered to pay compensation unless he proves that the impossibility arose from an outside cause in which he had no hand, and the court assesses it at the harm the creditor actually suffered when it occurred (article 264). A claim on an obligation is not heard against a party who denies it after fifteen years without a legal excuse, subject to special provisions (article 340). The period starts, in the ordinary case, on the day the debt becomes payable, for a conditional debt from the time the condition is met, and in a warranty-of-eviction claim from the time the right is established (article 344).

What the file should hold (practice, not codified)

Practice, not codified: a file on ending a contract can hold the signed contract and any termination clause, the record of the breach or impossibility and its date, the notice with proof of how and when it was sent, the reply, any written release, a record of what each side delivered and received, and the final account between them.

Common mistakes

  1. Leaving a valid binding contract on one's own decision, when it may be ended only by agreement or judgment (article 167).
  2. Treating an automatic termination clause as removing notice, when it does so only if the parties expressly agree (article 170).
  3. Demanding termination without first giving notice to the debtor (article 171).
  4. Claiming compensation without notice, when it is due only after notice unless a provision says otherwise (article 265).
  5. Releasing a contract by agreement when the subject no longer exists in the party's hand, outside the part that remains (article 169).
  6. Ignoring the return of what each side received after termination (article 173).
  7. Leaving the claim until it is barred by time (articles 340 and 344).

Hypothetical example

The following example is hypothetical and only illustrates the articles above.

A buyer and a seller have a contract binding on both sides, and the seller does not deliver. The buyer gives notice to the seller and demands termination (article 171). The court may order performance at once, allow a period, or rule termination, and it awards compensation if there is ground for it (article 171). If the contract is terminated, the parties are returned to their prior state, and if that is impossible the court awards compensation (article 173). If force majeure had made delivery impossible, the matching obligation would have lapsed and the contract would have terminated of its own accord (article 172).

Frequently asked questions

Can a party end a binding contract on its own decision?

No, a valid binding contract may be terminated or modified only by mutual agreement or by judgment (article 167).

What is a release between the parties?

It is termination between them and a new contract for third parties, made by offer and acceptance (articles 168 and 169).

Can the contract end automatically on breach?

Yes, by agreement, but notice is still needed unless the parties expressly waive it (article 170).

What does a party do when the other does not perform?

After notice to the debtor it may demand performance or termination, and the court decides (article 171).

What happens if force majeure makes performance impossible?

The matching obligation lapses and the contract terminates of its own accord (article 172).

When is notice not needed for compensation?

In the four cases listed in article 266, otherwise notice comes first (articles 265 and 266).

What follows termination?

The parties return to their prior state with the rights that follow, and compensation if that is impossible (article 173).