The Law and Who It Covers
Payment under a construction or works contract in Qatar is governed first by the contract and then by the contract-for-work rules of the Civil Code (Law No. 22 of 2004), articles 682 to 715. Article 682 defines the contract for work as a contract under which one party undertakes to make a thing or perform a work for the other party for a fee, without being subordinate to that party or acting as its agent. The party who undertakes the work is the contractor, and the other party is the owner.
The Tenders and Auctions Law (Law No. 24 of 2015) also applies to ministries, other government bodies, and public authorities and institutions, and articles 13, 19, 20, 21 and 24 of that law touch on payment. To the extent the relevant legislative instrument provides, it excludes the armed forces, police and other military bodies and the National Cyber Security Agency for confidential contracts set by Emiri decision, Qatar Energy, the Qatar Investment Authority, and bodies excluded by a Cabinet decision (article 2, first paragraph, of the issuing articles of Law No. 24 of 2015, as replaced by Law No. 17 of 2024). With the approval of the Prime Minister, on the Minister's proposal, a specific work, service or supply of an item may also be excluded from the application of the law (article 2 of the annexed law, as amended by Decree-Law No. 18 of 2018). In a private contract, the terms "payment certificate" and "retention" come from the contract, so the contract documents come first.
Measurement and Certification
The procedure for monthly measurement and the person who certifies come from the contract. Article 698 paragraph 1 deals with work made of distinct parts, or priced by unit: either party may ask for inspection after each part or section of enough importance to the work as a whole is finished. Where the contract sets its own measurement and certification steps, the contract governs how the quantities are measured and who signs.
The effect of payment is stated in article 698 paragraph 2. What the contractor's dues were paid for is presumed to have been inspected and accepted, unless it is shown that the payment was on account. A payment that the contract labels as on account therefore does not carry that presumption. This is why the wording of each certificate and payment matters.
Entitlement and the Time of Payment
Article 697 requires the owner to pay the contractor's dues when it receives the work, unless the agreement or custom provides otherwise. Article 698 paragraph 1 adds that, for work in distinct parts or priced by unit, the contractor may collect its dues in proportion to the work done, unless the agreement provides otherwise. In that situation the contractor collects its dues as the work proceeds, and interim payments are also available where the contract provides for them.
Article 699 applies where the dues were not agreed. They are then fixed by reference to the like value of the work at the time of the contract and the value of the materials the contractor supplied and the work needed. Article 700 provides that a rise in prices does not change the parties' obligations, subject to article 171 paragraph 2.
Article 693 deals with receipt. Once the contractor has finished, placed the work at the owner's disposal and notified the owner, the owner must take it over according to the usual dealings. If the owner refuses without a legitimate reason after a formal notice, the work is treated as delivered to it.
Retention and Government Contracts
The retention percentage and the time of its release come from the contract. A retention clause is a term of the contract, and its percentage, its stages and its release conditions are those the contract states.
For government contracts, article 13 of the Tenders and Auctions Law requires a provisional guarantee with each bid and a final guarantee from the successful bidder, with the Regulations setting the rules for each and the cases of exemption from them. Its second paragraph allows the government body to withhold a percentage of the total value of some contracts to secure performance, according to the rules the Regulations set. Article 19 allows advance payments on account, with the approval of the head of the body, against an approved unconditional bank guarantee of the same value and currency, valid until the actual due date of those sums. The percentage and the conditions are in the Regulations and in the contract.
Deductions, Delay Fines and Assignment
Article 21 of the Tenders and Auctions Law provides that a contractor who is late may be given an extra period and a fine for the period of delay, under the rules and percentages of the Regulations. The fine may be waived in whole or in part where the delay was for reasons beyond the contractor's control, or where the delay caused no damage, in the cases and by the decision-makers that article names. The fine does not affect the body's right to full compensation for damage caused by the delay.
Under article 24 paragraph 1, where the contract is terminated or executed at the contractor's expense, the final guarantee belongs to the government body, and the body may deduct the fines it is owed, or any loss it suffered, from any sums due or becoming due to the contractor with it or with any other government body, without any further step. Under paragraph 2, with the approval of the Prime Minister, on the reasoned recommendation of the Minister and after hearing the committee, and outside the cases in which the contract is treated as terminated under article 23, the contractor may be excused from all or some of the penalties that follow termination or execution at its expense. Article 20 provides that the contractor may not assign the contract or the sums due to it, in whole or in part, to another person without the approval of the head of the body.
Between private parties, the right to deduct is that of the contract and the general rules.
Variations and Notice
Where the contract was made on an estimated bill of quantities and it becomes clear during the work that the estimate must be exceeded appreciably to carry out the agreed design, article 708 paragraph 1 requires the contractor to notify the owner promptly and state the increase it expects, otherwise it loses the right to claim the increase. Under paragraph 2, if the excess is serious, the owner may withdraw and stop execution without delay, paying the value of the work done, estimated under the contract terms, without compensating the contractor for what it could have earned.
Under article 709, where the price is a lump sum for an agreed design, the contractor may not claim an increase because of a change or addition to that design, unless it results from the owner's act, or the owner authorised it and agreed with the contractor on what is due for it.
Final Account, Receipt and Guarantee
At receipt, article 696 provides that once the work has been received, actually or constructively, the contractor is no longer responsible for a defect or a breach of the contract terms that is apparent in it. If the defect or breach is hidden and the owner discovers it after receipt, the owner must promptly notify the contractor, having regard to the custom of the trade, otherwise it is taken to have accepted the work.
For buildings and fixed installations, article 711 paragraph 1 makes the contractor and the engineer jointly guarantee for 10 years any collapse, or total or partial defect, in what they built. Paragraph 2 starts the period from the date of receipt and allows a shorter period if the parties intended the structure to last less than 10 years. Article 714 provides that the guarantee claim lapses after three years from the collapse or the discovery of the defect. Article 715 makes void any condition that aims to exempt the engineer or the contractor from the guarantee or to limit it.
Under article 711 paragraph 2, the guarantee period runs from the date of receipt. The release of retention is a contract term, and article 711 paragraph 2 keys the guarantee period to receipt.
Practical Example (Hypothetical) and Critical Mistakes
Suppose an owner and a contractor sign a private contract for a building worth QAR 2,000,000. The contract says that monthly certificates are issued for the work done, that 10% is retained from each, that half of the retention is released at receipt and the other half 12 months later. These clauses are assumed for the example.
Three certificates cover work worth QAR 400,000, QAR 600,000 and QAR 1,000,000. The owner retains QAR 40,000, QAR 60,000 and QAR 100,000, so the retention is QAR 200,000, and the owner pays QAR 1,800,000 in total. If the contract marks each payment as on account, article 698 paragraph 2 does not presume that the paid work was accepted. If it does not, the presumption applies unless the contractor shows the payment was on account.
At receipt, QAR 100,000 falls due under the contract. The remaining QAR 100,000 falls due after 12 months. A hidden defect found in month 8 must be notified promptly under article 696 paragraph 2. Under article 711 paragraph 2, the ten-year guarantee period runs from receipt.
Common mistakes:
- Treating a payment as proof of acceptance without checking whether it was marked as on account.
- Assuming the Civil Code sets a retention percentage or a release date, when the contract does.
- Claiming an increase on an estimated or lump-sum contract without the prompt notice article 708 requires, or without the owner's act or authorisation that article 709 requires.
- Assigning sums due under a government contract without the approval article 20 requires.
- Giving late notice of a hidden defect after receipt.
- Treating the release of retention as settling guarantee questions, when article 711 paragraph 2 runs the guarantee period from receipt.
Frequently Asked Questions
Does Qatar law require monthly payment certificates?
Monthly certificates come from the contract. Article 698 paragraph 1 allows inspection and proportional collection for work in distinct parts or priced by unit, unless the agreement says otherwise.
What does a payment prove?
Under article 698 paragraph 2, what the dues were paid for is presumed inspected and accepted, unless it is shown that the payment was on account.
Is there a legal retention percentage?
The retention percentage comes from the contract. For government contracts, article 13 paragraph 2 of the Tenders and Auctions Law lets the body withhold a percentage of the total value of some contracts, according to the Regulations.
When are the contractor's dues payable?
Under article 697, when the owner receives the work, unless the agreement or custom provides otherwise. Article 693 treats the work as delivered if the owner refuses it without a legitimate reason after a formal notice.
Can a government body deduct fines from sums due?
Under article 24 paragraph 1 of the Tenders and Auctions Law, where the contract is terminated or executed at the contractor's expense, the body may deduct fines or losses from sums due or becoming due, without any further step. Paragraph 2 allows an exemption from all or some of those penalties, with the approvals it names. Article 21 sets the delay fine, with the waiver cases it names.
Does the contractor have to give notice of extra cost?
On an estimated bill of quantities, article 708 paragraph 1 requires prompt notice of a considerable excess, otherwise the right to the increase is lost. On a lump sum, article 709 allows an increase only if it results from the owner's act or the owner authorised it and agreed on the amount.
How long does the guarantee last after receipt?
For buildings and fixed installations, article 711 provides 10 years from receipt, or a shorter agreed period if the parties intended a shorter life. The claim lapses three years after the collapse or discovery of the defect under article 714.