Saudi Arabia

Developing a Renewable Energy Project in Saudi Arabia: Licence, Grid Connection and Sale of Output to the Energy Buyer

Scope and Competent Authority

This article covers what a local or foreign developer needs when building a renewable generation plant in Saudi Arabia, operating it, connecting it to the grid and selling its output. The framework rests on the Electricity Law issued by Royal Decree No. M/44 dated 16/5/1442H, and the Implementing Regulation of the Law concerning the tasks of the Water and Electricity Regulatory Authority, issued by decision No. 43/02 of the Authority's board dated 13/04/1443H, corresponding to 18/11/2021. The Law defines an electricity activity as including electricity generation and cogeneration from any energy source, transmission, distribution, trading, retail sale, the principal buyer activity and district cooling, and it defines energy as including electricity produced from conventional, renewable and nuclear sources (Article 1 of the Law). The Ministry of Energy prepares the policies and plans, including a long term plan for the electricity activity that sets the share of each energy source in the energy mix and the interconnection of the electricity grid (Article 3, paragraph 4 of the Law). The Authority issues the regulations and approves the qualification documents and the mechanisms for tendering electricity activity projects according to the rules and procedures it sets (Article 4, paragraphs 1 and 7 of the Law).

When a Licence Is Required Before Works Begin

No electricity activity may be carried out except after obtaining a licence, and the Authority may issue an exemption for certain activities as the regulations specify (Article 5, paragraphs 2 and 3 of the Law). The Implementing Regulation provides that, subject to its Articles 5 and 11, building a generation plant or expanding its capacity for generating electricity in it, and generating electricity in a generation plant, may be done only under a generation licence, and that this licence is required before construction works begin and throughout the period of the activity (Article 6, paragraph 1(a) of the Implementing Regulation). The same applies to building or expanding any part of a transmission system (transmission licence) and any part of a distribution system (distribution licence). Wholesale electricity trading and the principal buyer activity each have their own licence, required throughout the period of the activity (Article 6, paragraph 1(c), (d), (e) and (g) of the Implementing Regulation). The board may reclassify electricity activities by adding activities, dividing existing ones or cancelling some (Article 6, paragraph 2 of the Implementing Regulation). In practice, starting construction before the generation licence is issued means starting an electricity activity without a licence, which the Law lists as a violation (Article 17, paragraph 1 of the Law).

The Permit for Preparatory Works

A person who intends to carry out preparatory works, including preparing plans and studies, in order to start an electricity activity that requires a licence or an exemption may apply to the Authority for a permit before starting those works. The Authority decides within no more than ten working days from the date the information in the application is complete (Article 5, paragraphs 1 and 2 of the Implementing Regulation). The permit holder must follow the Authority's conditions, which may include giving it information on the progress of the works and notifying it of any change in the proposed capacity (Article 5, paragraph 3 of the Implementing Regulation). The holder may not carry on the activity until it obtains the licence or exemption. The permit is not an indication that its holder meets the legal or technical requirements, and it does not signal the Authority's approval to issue the licence. The Authority may grant similar permits to other persons for the same activity, at the same time and in the same geographic area (Article 5, paragraphs 4, 5 and 6 of the Implementing Regulation). A permit therefore gives the developer no exclusive right to the site or the project.

Applying for the Licence, the Decision Period and Renewal

The application is made on the form approved by the Authority with its annexes. It includes the applicant's name and address, a description of the electricity activity, the geographic area and the details of the facilities, proof of financial capability and of technical capability and experience, proof that the facilities and equipment conform to the objectives of the Law and to the technical, health, safety and environmental requirements, disclosure of any shares or interests the applicant holds in, or control over, another licensee or licence applicant above the limits the board sets, and disclosure of the names of the executives of the activity. The Authority may refuse the application, or refuse renewal, if it objects to any of the names, and it may object to them while the licence is in force (Article 7, paragraph 1 of the Implementing Regulation). The Authority decides to grant, refuse or exempt within no more than 30 working days from the date the application is complete. A refusal must state reasons, and the application is treated as refused if the period passes without a decision. An applicant who is refused, or whose application is not decided within 30 working days of completion, may file a grievance before the Administrative Court under the legal procedures (Article 5, paragraph 4 of the Law, and Article 7, paragraph 2 of the Implementing Regulation). A licensee that intends to apply for renewal must complete the renewal requirements 90 days before its licence expires (Article 8 of the Implementing Regulation). Licence conditions include its term, taking into account the design life of the plants, lines and other facilities, the scope of the activity, prohibited activities and conditions on ownership, the level of separation between electricity activities, compliance with the codes and standards, and payment of the licence fee (Article 10, paragraph 1 of the Implementing Regulation). The licensee pays an annual fee within 30 days of its due date, and a non refundable payment is made when the application is submitted for its review (Article 12, paragraph 1 of the Implementing Regulation).

Amending and Ending the Licence

A licensee may apply to amend or end its licence, and the Authority must decide within 30 working days from the date the application is complete (Article 9, paragraph 1 of the Implementing Regulation). The Authority may amend or end a licence based on a condition in it, or under its powers in the Law, its Organization or the Implementing Regulation, and it notifies the licensee before the decision so that the licensee can submit observations within the period the Authority sets (Article 9, paragraphs 2 and 3 of the Implementing Regulation). If a licensee is unable to carry out the licensed activity, the Authority must take the arrangements needed to keep the service going (Article 5, paragraph 6 of the Law), and the licensee bears the costs and burdens of those arrangements as the licence conditions provide (Article 10, paragraph 1(k) of the Implementing Regulation).

Assigning the Licence, Pledging Assets and Exclusivity

Before obtaining the Authority's written permission, a licensee may not assign its licence or transfer ownership of the licensed assets, whether by sale, pledge or any other way. The Authority sets conditions for this, provided the act does not disrupt the electricity activity (Article 5, paragraph 5 of the Law). The Implementing Regulation adds that the licensee notifies the Authority and gives it what it requests, that no such act is treated as concluded or effective without the written approval, and that the Authority may approve with conditions and amend the licence, require the fee set for reviewing the request, or refuse approval (Article 10, paragraph 4 of the Implementing Regulation). These rules apply to permits and exemptions too, and the Authority may exclude what does not suit a given permit or exemption (Article 10, paragraph 5). The Authority may also grant similar licences to other persons for the same activity, at the same time and in the same area, and a licensee may not claim an exclusive right unless the licence expressly states it (Article 10, paragraphs 2 and 3 of the Implementing Regulation). A pledge over project shares or assets in favour of lenders therefore needs a review of the licence conditions and the Authority's written approval before it can be relied on.

Exemption from the Licence or Some of Its Requirements

The Authority may exempt a project from some requirements of a generation or cogeneration licence if all of these conditions are met: the plant is not connected to a transmission or distribution system, unless those systems are themselves exempt from licensing; all the electricity or cogeneration output is, or will be, consumed exclusively by the plant owner and its wholly owned affiliated facilities; and connecting the facility to the network of the distribution or transmission licensee is not possible, except in cases the Authority decides (Article 11, paragraph 1 of the Implementing Regulation). Exemption from a transmission or distribution licence is possible if the electricity transmitted or distributed is consumed exclusively by the owner of the lines and its wholly owned affiliated facilities (Article 11, paragraph 2). The Authority may also exempt some activities from applying for a licence as the rules and procedures it issues provide (Article 11, paragraph 3). A project that sells its output to another buyer does not meet the condition of exclusive consumption by the plant owner and its affiliated facilities.

Access to Property and Site Rights

A licensee has the right to reach its equipment and installations within the necessary limits up to the point where its system connects to the system of one of its customers, to the extent and in the manner the regulations specify (Article 7, paragraph 2 of the Law). The developer should distinguish this right tied to the licence from the contractual rights over the site that it obtains from the owner before the licence is issued.

Connecting the Project to the Grid and Using It

Any licensee may, when needed, use a transmission or distribution system owned by another licensee or connect to it for a fee and without discrimination, in accordance with the Law and the regulations. The owner of the network issues the network code at the Authority's request, and the Authority approves it and reviews it periodically (Article 16 of the Law). The transmission and distribution licensee must allow connection to, or use of, its system to any consumer that requests it under the approved rules, and must give a written offer for connection or use if a licensee requests it within the period the Authority considers appropriate (Article 13, paragraphs 1 and 2 of the Implementing Regulation). The offer must comply with the Law, the Implementing Regulation and the rules, including requiring the applicant to comply with the codes and standards. It stays valid for a reasonable period the Authority sets, must be clear, transparent, objective and non discriminatory, and includes a connection agreement or a system use agreement as requested (Article 13, paragraphs 3, 4 and 5). Information received from applicants may be used only for the purpose for which it was given (Article 13, paragraph 6(c)). Entering into a connection or use agreement may be refused only in three cases. The first is where connection or use would cause, or is likely to cause, serious danger, harm or injury to a person or damage to property. The second is where it would cause serious danger to the licensee's system or interfere with its operation, unless the danger arises from the licensee's own failure to maintain and improve the system under the codes, in which case it must remove the cause within a reasonable period the Authority sets and then accept the request. The third is where connection or use does not conform to the approved codes and rules and no alternative technical solutions can be reached (Article 14 of the Implementing Regulation). Transmission and distribution licensees may not discriminate between those connected and their categories in terms and conditions, except for objective reasons the Authority approves or by express provision, and if the Authority notifies them of unjustified discrimination they must give a justification that satisfies it or end the discrimination immediately (Article 16 of the Implementing Regulation).

Buying the Output, Its Price and Purchase Agreements

The Law defines the principal buyer as the licensee for energy purchase, or any successor the Authority designates, that carries out the trading activity and tenders generation projects as the Authority specifies in the licence (Article 1 of the Law). The Implementing Regulation adds participation in tendering generation or cogeneration projects (Article 1 of the Implementing Regulation). A licensee may agree, through direct commercial negotiation with another licensee or a large consumer, on a price for its services that differs from the approved tariff, as the regulations specify (Article 12, paragraph 3 of the Law). For this the Implementing Regulation provides that two licensees, or a licensee and a large consumer, may agree on a price or prices for electricity services according to the rules and procedures the Authority issues, on condition that the Authority is notified of the agreement in advance and raises no objection within 30 working days of the notice. If the Authority objects, the parties must amend the agreement taking the objection into account and resubmit it (Article 28 of the Implementing Regulation). This condition governs the parties' agreement and is not a duty placed on the Authority, and how a notice is handled follows the Authority's rules and procedures. The Law requires a licensee to register with the Authority any agreement it concludes with another licensee or with consumers that relates to price, tariff, the right to use the transmission or distribution network or the assets tied to the electricity activity, as the regulations specify. The Implementing Regulation requires registration of any agreement it concludes with another licensee or with consumers within a maximum of 20 working days from the date it is concluded. Any provision in an agreement concluded after the Law takes effect that conflicts with the Law, the Organization or the regulations is void, and registered agreements are treated as confidential and the Authority uses their information only for its regulatory tasks (Article 13, paragraph 1 of the Law, and Article 37 of the Implementing Regulation). The Authority may approve or refuse those agreements. On the move to an electricity market, the Law protects the rights of investors who develop projects, on condition that the investor is not in a dominant position, by securing the return on their investment agreed with the party that bought their products, by preserving their rights through the commercial agreement between them and that party, or by exempting them from participating in the market (Article 15 of the Law).

Competition, Mergers and Acquisitions

A licensee may not enter into any agreement or arrangement that obstructs or restricts competition in the electricity activity, and any such step is void. A licensee in a dominant position may not breach regulatory instructions, including those that restrict competition (Article 13, paragraphs 2 and 3 of the Law). A licensee must obtain the Authority's approval before merging with other persons or acquiring most of their shares or assets, and must notify the Authority of any preliminary agreement. It must also obtain approval before buying 5% or more of the shares of another licensee, or its securities or any other form of equity, or acquiring a lower percentage if it creates a dominant position in any part of the electricity activities (Article 13, paragraphs 4 and 5 of the Law). The Authority decides on a merger or acquisition request within no more than 30 working days from the date the information and data are complete (Article 39, paragraph 4 of the Implementing Regulation). This matters to a developer that holds more than one licensed project or buys a stake in a licensed project company.

Violations, Penalties and Grievance

Violations include carrying out an electricity activity without a licence or exemption, failing to comply with a decision of the Authority, to provide the information it requests, or to obtain the approvals required under the Law, the regulations and the licence or exemption conditions, giving false or misleading information, using the electricity system or connecting to it unlawfully, and failing to meet the approved fuel efficiency standards and the environmental, safety and public health specifications and standards (Article 17 of the Law). Without prejudice to a more severe penalty in another law, anyone who violates the Law, the regulations or the licence or exemption conditions is punished by one or more of these penalties: suspension of the activity in whole or in part for no more than one year, cancellation of the licence, and a fine of no more than ten million riyals (Article 18, paragraph 1 of the Law). The competent committee may impose a fine of no more than 10% of the value of the original violation for each day the violation continues after notice of its decision, double the fine if the same violation is repeated within three years of the earlier violation, and require the violator to return the sums it collected because of the violation. It may also include in the penalty decision publication of its operative part at the violator's expense, in a local newspaper issued where the violator resides or, if there is none at its seat, in the nearest region, or in another suitable medium according to the type, gravity and effects of the violation, and publication takes place only after the decision becomes final by the lapse of the statutory period or is affirmed by the competent court (Article 18, paragraph 3). In urgent and necessary cases the Authority, by decision of the Governor or his delegate, may require the violator to stop and to correct the situation, suspend its activity for no more than six months, or take what is needed to manage the activity temporarily for a specified period of no more than six months, renewable once, so that the activity continues, according to the rules and procedures the regulations specify, and the violation is referred to the committee within ten working days of the decision (Article 20 of the Law). An objection to the committee's decisions is brought before the Administrative Court within 60 days of notification of the decision, and the objection does not stay execution (Article 19, paragraph 5 of the Law). Parties to a dispute in the electricity sector may ask the Authority to settle it amicably as the regulations specify, without prejudice to other settlement means in the agreements in force (Article 19, paragraph 1).

Hypothetical Example

This is a hypothetical example, not a real case. A licensed renewable generation company, owned by a foreign investor and a local partner, wants to change the conditions of its licence after commissioning. It applies to the Authority to amend the licence, and the Authority must decide within 30 working days from the date the application is complete. If the Authority itself considers amending or ending the licence, it notifies the company before deciding so that the company can submit its observations within the period the Authority sets. As the licence nears expiry, the company completes the renewal requirements 90 days before it expires and pays the annual licence fee within 30 days of its due date. The example shows the order of the steps and does not set an actual project timeline.

Frequently Asked Questions

May construction of the renewable generation plant start before the generation licence is issued

No, subject to Articles 5 and 11 of the Implementing Regulation. The generation licence is required before construction of the plant begins and throughout its operation. The permit covers only preparatory works such as plans and studies and does not allow the activity to be carried on (Article 6, paragraph 1(a) and Article 5, paragraphs 1 and 4 of the Implementing Regulation).

How long does the Authority have to decide on a licence application and what if it does not decide

The Authority decides within no more than 30 working days from the date the application is complete. A refusal must state reasons, and the application is treated as refused if the period passes without a decision. The applicant may file a grievance before the Administrative Court under the legal procedures (Article 5, paragraph 4 of the Law and Article 7, paragraph 2 of the Implementing Regulation).

Does the licence give exclusivity over an area or a project

Not by default. The Authority may grant similar licences to other persons for the same activity, at the same time and in the same area. It may allow a licensed activity to be exclusive for a specific purpose and geographic area, for the whole licence term or part of it, and a licensee may not claim an exclusive right unless the licence expressly says so (Article 10, paragraphs 2 and 3 of the Implementing Regulation).

May the project assets be pledged to lenders

Only after the Authority's written permission. The licence may not be assigned and ownership of assets may not be transferred by sale or pledge before it, no act is treated as concluded or effective without the written approval, and the Authority may approve with conditions or refuse (Article 5, paragraph 5 of the Law and Article 10, paragraph 4 of the Implementing Regulation).

Must the power purchase agreement be registered with the Authority

Yes. A licensee must register with the Authority any agreement it concludes with another licensee or with consumers within a maximum of 20 working days from the date it is concluded, without prejudice to the Authority's right to approve or refuse the agreement (Article 37, paragraph 1 of the Implementing Regulation). A price agreement between two licensees, or between a licensee and a large consumer, is separate: it follows the Authority's rules and procedures and is conditional on prior notice to the Authority and no objection from it within 30 working days of the notice. That condition governs the parties' agreement and is not a duty placed on the Authority (Article 28 of the Implementing Regulation).

May the grid owner refuse to connect the project

Only in three cases: serious danger, harm, injury or damage to property; serious danger to its system or interference with its operation; or non conformity with the approved codes and rules with no alternative technical solution (Article 14 of the Implementing Regulation).

Does buying a stake in another licensee need approval

Yes if the stake is 5% or more of the shares of another licensee, or of its securities or another form of equity, or if it is lower but creates a dominant position in any part of the electricity activities. Approval of the Authority must be obtained before the purchase (Article 13, paragraph 5 of the Law and Article 39, paragraph 1(b) of the Implementing Regulation).

Back to Blog