Saudi Arabia

Data Center Construction and Equipping Contract and Acceptance Testing in Saudi Arabia

A contract to build and equip a data center in the Kingdom of Saudi Arabia is a muqawala (works) contract governed at its core by the Civil Transactions Law, promulgated by Royal Decree No. M/191 of 29/11/1444 H., specifically the muqawala provisions from article 461 to article 478, together with the law's general rules on contracts, compensation and rescission. The contract rests on two linked obligations: the contractor must complete the work according to the contract conditions and within the agreed time, and the employer must promptly take delivery of the work and pay the price. This article explains how the clauses on design, capacity, power, cooling, fire protection, security, testing, the program and the warranty are built on these provisions.

1. The legal frame: an independent works contract

A muqawala is a contract under which the contractor undertakes to make a thing or perform work in return for a wage, without being subordinate to the employer or acting as its deputy (article 461). The contractor's obligation to perform the work may validly use materials supplied by the contractor or by the employer (article 462), and on this the two supply models are built: either the contractor supplies all or some of the equipment and materials, or the employer supplies the devices, servers and units and the contractor installs and commissions them. The choice between the two models determines who guarantees the specifications of the materials, who safekeeps them and who returns the surplus.

2. Design and specifications

If the employer stipulates that the contractor supply all or some of the materials, the contractor is responsible for the agreed conditions and specifications being met where they exist, and otherwise is bound to supply materials fit for the intended purpose according to custom (article 463(1)). If it is the employer who supplied the materials, the contractor is bound to preserve them with the care of the ordinary person, to observe the technical norms in its work and to return what remains of them to the employer (article 463(2)). The contractor must complete the work according to the contract conditions and within the agreed time; where there are no conditions or no agreed time, it must complete it according to recognized practice and within the reasonable time required by the nature of the work (article 465). For this reason the agreed design must be a document incorporated into the contract, because the lump-sum, bill-of-quantities and variation rules all revolve around that design.

3. Capacity, power and cooling as contractual specifications

The law fixes no technical figures for electrical capacity, cooling capability or target uptime; all of these are contractual content set by the parties. The statutory rules that carry them are that the contractor is responsible for the agreed conditions and specifications (article 463(1)), that the work must be completed according to the contract conditions (article 465), and that a contract must be performed according to its content and in a manner consistent with what good faith requires (article 95). Capacity, power and cooling targets should therefore be written into the contract in measurable form and tied to acceptance criteria and tests, so that they do not turn into an unmeasurable general description at handover.

4. Fire protection and security as specification items

Fire suppression, detection, access control and monitoring systems are parts of the agreed work, and the same rules apply to them as to the rest of the work: the contractor's responsibility for the agreed specifications (article 463(1)), the duty to complete according to the contract conditions and recognized practice (article 465), and the rules on correction while work is in progress (article 466). The contract should fix for each such system its specification, its technical source and the manner in which it will be examined at acceptance.

5. The program and delay

The contractor must complete the work within the agreed time (article 465). If the contractor delays starting the work or completing it to a degree that gives no hope of finishing within the agreed time, the employer may request rescission of the contract at once (article 466(2)). If a debtor delays performance of its obligation, it must compensate the creditor for the harm caused by the delay, unless it proves that the delay in performance was for a cause beyond its control (article 171). The two parties may also fix the amount of compensation in advance by stipulating it in the contract or in a later agreement, unless the subject of the obligation is a cash sum, and no notice is required for it to fall due (article 178). The program in a data center construction contract is not an administrative annex; it is a material condition to which the rules of rescission and compensation attach.

6. Price: lump sum or bill of quantities by unit

If the muqawala is concluded on an agreed design for a lump-sum price, the contractor may not claim any increase in the price even if the prices of the materials used in the work rise or the wages of workers or other expenses rise (article 471(1)). If a modification or addition occurs in the design, the contractor may not claim any increase in the price unless it resulted from the employer's error or was made with the employer's permission and an increase was agreed with the contractor (article 471(2)). If, instead, the contract is concluded on a bill of quantities priced by unit and it becomes clear during the work that executing the agreed design requires a manifest exceeding of the estimated bill, the contractor must at once inform the employer, stating the amount of the expected increase in the price; if it does not, its right to claim the expenses exceeding the bill's value lapses (article 470(1)). If the exceeding required by the design is substantial, the employer may withdraw from the contract and stop performance, without delay, while paying the contractor the value of the works it completed, assessed according to the contract terms (article 470(2)). If the contractor's wage is not fixed in the contract, it is entitled to the wage of the like for its work plus the value of the materials it provided that the work requires (article 472).

7. Correction while work is in progress

If the contractor breaches the contract conditions while work is in progress, the employer may serve notice on it to comply with them and correct the work within a reasonable time that the employer fixes; if that time expires without correction, the employer may engage another contractor to complete or correct the work at the first contractor's expense, or may request rescission of the contract (article 466(1)). The employer may request rescission at once if repairing the defect is impossible or if the delay prevents completion within the time (article 466(2)). Monitoring the progress of the work with periodic minutes is not administrative luxury; it is what proves the notice and fixes when the reasonable time expired.

8. Loss or damage to the thing before delivery

If the thing is destroyed or damaged before delivery to the employer for a cause the contractor had no hand in, the contractor may not claim the agreed wage or the expenses it bore, unless the employer was at the time of the destruction or damage in breach of its obligation to take delivery of the work (article 467(1)). If the materials were supplied by the employer and the thing is destroyed or damaged before delivery to it for a cause the contractor had no hand in, the employer may not claim their value from the contractor, unless the contractor at the time of the destruction or damage had been given notice for breaching its obligation to deliver the work, and it is not proved that the thing would have been destroyed or damaged had it delivered without breaching its obligation (article 467(2)). This rule makes the time of delivery and its minute the point at which risk passes, and so the date on which the work was placed at the employer's disposal must be fixed in writing.

9. Delivery and acceptance testing

If the contractor completes the work and places it at the employer's disposal, the employer is bound to take the initiative to take delivery of it; if the employer refuses without legitimate reason despite being informed, and the thing is destroyed or damaged in the contractor's hands without the contractor's transgression or fault, the contractor is not bound to compensate (article 468). The employer must pay the wage on taking delivery of the agreed work, unless otherwise agreed (article 469(1)). If the work consists of several parts, or the wage is fixed on a unit basis, the employer must pay the contractor for the work completed, after inspecting and accepting it, provided that what has been completed is distinct or significant in relation to the work as a whole (article 469(2)). Acceptance testing in a data center construction contract is the practical application of the inspection-and-acceptance rule: the contract fixes the tests, their success criteria, their duration and the body that runs them, and acceptance then triggers the entitlement to the price and the passing of risk.

10. The warranty after acceptance

The post-acceptance warranty rests on the law's general rules: the contractor is bound to complete the work according to the contract conditions (article 465); the employer may serve notice on the contractor to correct what breaches the conditions, then engage another contractor at its expense or request rescission (article 466); the amount of compensation may be fixed in advance in the contract, unless the subject of the obligation is a cash sum (article 178); the agreed compensation is not due if the debtor proves that the creditor suffered no harm; the court may reduce it if the debtor proves that it was exaggerated or that the original obligation was partly performed; the court may increase it to equal the harm if the creditor proves that the harm exceeded it because of the debtor's fraud or gross error; and any agreement contrary to these rules is void (article 179). The duration and scope of the warranty are contractual content that the parties fix expressly: which works and equipment it covers, what it excludes, how long it runs, and the manner of reporting a fault and the time for repair.

11. Subcontracting and suppliers

The contractor may assign performance of all or part of the work to a subcontractor, unless statutory texts, the agreement or the nature of the work require otherwise, or the contractor's person was a consideration in the contract (article 473(1)), and the contractor's liability toward the employer remains (article 473(2)). The subcontractor may not claim for itself from the employer anything of what is owed to the contractor, unless the contractor refers it to the employer (article 474). Equipping a data center relies on specialist suppliers for power, cooling and fire protection; assigning the specialist works is permissible in principle, but the main contractor's full responsibility for them does not shift.

12. End of the contract and exceptional circumstances

The muqawala contract ends on completion of the agreed work (article 475). Either party may request rescission of the contract if a sudden excuse connected with its performance arises for it, and it must compensate the other party for the harm arising from that rescission (article 476). If the contractor begins performance and then becomes unable to complete it for a cause beyond its control, it is entitled to the value of the works completed and what it spent on the work not completed, to the extent of the benefit that accrued to the employer (article 477). If the contractual balance between the parties' obligations collapses because of general exceptional circumstances that could not have been expected at contracting, so that the basis on which the contract's financial estimate was made falls away, the court may, according to the circumstances and after weighing the two parties' interests, order a restoration of the contractual balance, including extending the performance time or increasing or reducing the price, or may order rescission of the contract (article 471(3)). In contracts binding on both parties, if performance of the obligation becomes impossible for a cause the debtor had no hand in, its obligation and the obligation corresponding to it lapse and the contract is rescinded automatically (article 110); the two parties return to the state they were in before contracting, and if that is impossible the court may award compensation (article 111). Without prejudice to statutory provisions, rescission of the contract does not remove the dispute-settlement clause or the confidentiality clause, unless otherwise agreed (article 113).

13. The contract document file

Before signing, the parties complete a file evidencing: the agreed design incorporated into the contract, because the lump-sum, bill-of-quantities and variation rules all revolve around it; measurable specification schedules for capacity, power, cooling, fire protection and security; the program, its stages and what follows from delay at each stage; the acceptance-test plan, its success criteria, its duration and the body that runs it; an express clause on the supply model: who provides the materials and equipment; an express warranty clause with its duration, scope and fault-reporting mechanics; a clause on the permitted subcontracting; and standard forms for the minutes of placing the work at disposal and of inspection and acceptance.

14. Six common serious errors

First error: signing without incorporating the agreed design; the lump-sum, bill-of-quantities and variation rules all assume a defined design (articles 470 and 471).

Second error: drafting capacity, power and cooling targets in general unmeasurable terms; statutory responsibility rests on the agreed conditions and specifications (articles 463 and 465).

Third error: not fixing in writing the moment the work was placed at the employer's disposal; the passing of the risk of destruction and damage revolves around it (articles 467 and 468).

Fourth error: letting the employer withhold taking delivery without informing it in writing; its refusal without legitimate reason after being informed carries defined consequences when the thing is destroyed or damaged in the contractor's hands (article 468).

Fifth error: neglecting to inform the employer at once when exceeding the bill is expected in a unit-price contract; silence forfeits the contractor's right to the increase (article 470(1)).

Sixth error: settling for a verbal promise of operating warranty after acceptance; the warranty's duration, scope and fault-reporting mechanics are contractual content that must be written (articles 465 and 466, and article 178 with its exception for cash obligations).

15. Hypothetical worked example

The contractor began fitting out the data center under a lump-sum price. After contracting, general exceptional events that could not have been anticipated at the time of contracting struck the market, so that the financial basis on which the estimate had been built collapsed and the equilibrium between the obligations of the two parties broke down. Here the court may, as the circumstances require and after weighing the interests of the two parties, order the restoration of the contractual equilibrium, including extending the execution period or increasing or reducing the price, or order rescission of the contract (article 471(3)). The example shows why the contract file should record the data on which the price was built: those records are what let the court see the equilibrium the parties originally struck.

Frequently asked questions

1. When must the employer take delivery of the work?

If the contractor completes the work and places it at the employer's disposal, the employer is bound to take the initiative to take delivery of it; if it refuses without legitimate reason despite being informed, and the thing is destroyed or damaged in the contractor's hands without the contractor's transgression or fault, the contractor is not bound to compensate (article 468).

2. When must the employer pay the wage?

The employer must pay the wage on taking delivery of the agreed work, unless otherwise agreed (article 469(1)).

3. What must the contractor do if a unit-price bill will be exceeded?

The contractor must at once inform the employer that executing the agreed design requires a manifest exceeding of the estimated bill, stating the amount of the expected increase; if it does not, its right to claim the expenses exceeding the bill's value lapses (article 470(1)).

4. What can the employer do if the required exceeding is substantial?

If the exceeding required by executing the design is substantial, the employer may withdraw from the contract and stop performance, without delay, while paying the contractor the value of the works it completed, assessed according to the contract terms (article 470(2)).

5. Can the contractor claim a price increase under a lump-sum contract?

No. If the muqawala is concluded on an agreed design for a lump-sum price, the contractor may not claim any increase even if material prices or workers' wages or other expenses rise (article 471(1)).

6. Can the contractor claim an increase for a design change?

Only in two cases: if the modification or addition in the design resulted from the employer's error, or if it was made with the employer's permission and an increase in the price was agreed with the contractor (article 471(2)).