A company that lets another business handle personal data for it has to decide what the agreement with that business must say. The Personal Data Protection Law (Royal Decree No. M/19 of 1443/2/9, as amended by Royal Decree No. M/148 of 1444/9/5) sets the duty to choose a processor with the necessary guarantees in article 8. The Implementing Regulation lists what the agreement includes in article 17, together with the rules on instructions, checks, liability and subprocessors.

Four points drive most agreements: the content list in article 17(1), clear written instructions from the controller, prior approval for every subprocessor, and prompt notice to the controller of a leak (Regulation, articles 17 and 24). Choosing a processor does not end the controller's responsibility towards the data subject or the competent authority (Law, article 8).

Roles and choosing a processor

The controller is the public body or the natural or private legal person that decides the purpose and manner of processing, whether it processes the data itself or through a processor. The processor processes personal data for the benefit of the controller and on its behalf (Law, article 1). When choosing a processor, the controller must pick one that gives the necessary guarantees to apply the Law and the Regulations and must check that the processor complies. This does not reduce the controller's responsibility towards the data subject or the competent authority, and the Regulations deal with any later contracts the processor makes (Law, article 8).

What the agreement includes

The agreement with the processor includes the following (Regulation, article 17(1)). First, the purpose of the processing. Second, the categories of personal data processed. Third, the duration of the processing. Fourth, the processor's duty to notify the controller of a leak of personal data, without undue delay. Fifth, a statement of whether the processor is subject to the laws of other countries and what effect that has on its compliance with the Law and the Regulations. Sixth, no requirement that the processor obtain the controller's prior approval before a disclosure that is mandatory under the rules in force in Saudi Arabia, with the processor notifying the controller of that disclosure. Seventh, the subprocessors that contract with the processor, or any other party to which the data will be disclosed.

Where data is to be moved outside Saudi Arabia or disclosed to a party outside it, the Law sets conditions in article 29, among them that the move does not harm national security or vital interests, that the level of protection abroad is adequate under an assessment by the competent authority, and that it is limited to the minimum data needed. The Regulations set the details and the cases of exemption (Law, article 29).

Instructions and liability

The controller must give its instructions to the processor clearly. If an instruction breaches a rule in force in Saudi Arabia, the processor must tell the controller in writing and without delay. When the processor breaches the controller's instructions or the agreement, it is treated as a controller and is responsible for the breach of the Law (Regulation, article 17(2) and (4)).

Subprocessors

Before it contracts with a subprocessor, the processor must take sufficient safeguards so that the contract does not weaken the level of protection of the data, choose a party that gives the guarantees needed to apply the Law, and obtain the controller's prior approval. The controller is notified before the contract is made and can object within a period agreed between the controller and the processor (Regulation, article 17(5)).

Security and leaks

The controller must take the organizational, administrative and technical measures that keep personal data secure, including when it moves, and must follow the controls of the National Cybersecurity Authority or, if it is not bound by them, recognized cybersecurity good practice (Law, article 19; Regulation, article 23). If a leak is likely to harm the data or the data subject, or to conflict with the data subject's rights or interests, the controller notifies the competent authority within 72 hours of learning of it. Missing details are provided as soon as possible with the reasons for the delay. The controller also tells the data subject without undue delay where harm is likely (Regulation, article 24). The processor's duty to notify the controller is a term of the agreement (Regulation, article 17(1)).

Audit and deletion

The controller is responsible for checking, periodically, that the processor carries out the processing as the Law and the Regulations require, whether the processing is done by the processor or by another party for it. It may appoint an independent party to review compliance on its behalf (Regulation, article 17(3)). The controller destroys personal data without delay once the purpose of collection has ended, but it keeps the data where a statutory basis requires keeping it for a set period, or where the data is closely tied to a case before a court (Law, article 18). When it destroys data, it takes suitable steps to notify the parties it disclosed the data to and ask them to destroy it, and it destroys every copy in its systems, backups included (Regulation, article 8(2)).

Working order

The following is suggested practice, not a requirement of law. Write the agreement as one document that follows the list in article 17(1), item by item. Add a clause on how the processor helps the controller answer data subject requests, which the controller must answer within the period set by the Regulations (Law, article 21). Add a clause on what happens to the data at the end of the agreement, in line with the deletion rules. Keep a list of approved subprocessors and the date of each approval. Record each check of the processor and each leak notice with its date.

Hypothetical example

This example is hypothetical and the facts are invented. A retailer in Riyadh uses a payroll software provider as its processor. The agreement states the purpose (monthly payroll), the categories of data (names, ID numbers and salaries), a duration of 24 months, the provider's duty to report a leak without undue delay, the foreign law the provider is subject to, and one named subprocessor for hosting (Regulation, article 17(1)). Later the provider wants to add a support company in another country. It notifies the retailer first and obtains its approval, and the retailer has the agreed period to object (Regulation, article 17(5)). Months later the provider finds a leak and tells the retailer at once. The retailer, if the leak is likely to cause harm, notifies the competent authority within 72 hours of learning of it (Regulation, article 24).

Frequently asked questions

Must a written agreement with the processor include a purpose and a duration?

The agreement includes the purpose of the processing, the categories of data and the duration of the processing (Regulation, article 17(1)).

Does the controller stay responsible after choosing a processor?

Yes. Choosing a processor does not reduce the controller's responsibility towards the data subject or the competent authority (Law, article 8).

Can the processor use a subprocessor?

Yes, with the controller's prior approval, notice before the contract and a chance to object within an agreed period (Regulation, article 17(5)).

What happens if the processor breaches the controller's instructions?

It is treated as a controller and is responsible for the breach of the Law (Regulation, article 17(4)).

Who checks that the processor complies?

The controller, periodically, and it may appoint an independent party to do the review (Regulation, article 17(3)).

When must a leak be notified?

The controller notifies the competent authority within 72 hours of learning of a leak likely to cause harm (Regulation, article 24). The processor must notify the controller without undue delay (Regulation, article 17(1)).

What happens to the data when the processing ends?

The controller destroys it without delay once the purpose has ended, unless a statutory basis requires keeping it for a set period or it is tied to a court case (Law, article 18).