When a party to a commercial contract cannot perform, or performance becomes far more expensive than expected, the answer depends on what actually happened. The Civil Transactions Law, issued by royal decree number M/191 of 29/11/1444H, separates impossibility of performance, which ends the obligation, from general exceptional circumstances that make performance burdensome, which open a route to renegotiation and then to adjustment of the obligation. The contract's own clauses also allocate risk.
Three different tools, not one
The Law handles the question in three ways. The first is impossibility of performance for a cause outside the debtor's control (arts 110 and 294). The second is general, unforeseeable exceptional circumstances that make performance burdensome (art 97). The third is what the parties agreed in the contract (arts 173 and 174). Mixing them up is the most common way a party weakens its position when it relies on an event.
Impossibility in reciprocal contracts
If performance of an obligation becomes impossible for a cause outside the debtor's control, the debtor's obligation and the corresponding obligation lapse, and the contract is dissolved automatically (art 110(1)). Article 294 provides that the debtor's obligation lapses if the debtor proves that performance has become impossible for a cause outside the debtor's control, and the corresponding obligation lapses too, if there is one.
The two requirements are impossibility and a cause outside the debtor's control. The burden of proof is on the debtor under art 294, and also under art 170, which bars an award of damages if the debtor proves that the non-performance was for a cause outside the debtor's control.
Partial and temporary impossibility
If the impossibility is partial, the obligation lapses only for the impossible part and its counterpart. The same rule applies to temporary impossibility in continuing contracts. In both cases the creditor may ask for rescission, and the court may refuse rescission if the impossible part is of minor importance compared with the obligation (art 110(2)).
So a two-month stoppage of supply caused by an event outside the supplier's control, in a continuing supply contract, does not automatically end the whole contract. The impossible part and its counterpart lapse, the creditor may ask for rescission, and the court assesses how important the impossible part is.
General exceptional circumstances and higher costs
Higher cost alone is not impossibility. Article 97 deals with it on conditions: general exceptional circumstances arise, they could not have been foreseen when the contract was made, and as a result performance becomes burdensome for the debtor so that it threatens a heavy loss. The debtor may then, without unjustified delay, invite the other party to negotiate.
Asking to negotiate does not entitle the debtor to withhold performance. If no agreement is reached within a reasonable period, the court, depending on the circumstances and after weighing the interests of both parties, may reduce the burdensome obligation to a reasonable level. Any agreement contrary to the article is void. The outcome is an adjustment of the obligation by the court, not its extinction.
Proof: what the debtor needs to show
These articles rest on facts that must be shown: the event, that it was outside the debtor's control, and its effect on the specific obligation (impossible or only burdensome, total or partial, permanent or temporary). Article 175 requires a formal warning before damages are due, unless the parties agreed otherwise or a legal provision says otherwise. Article 97 requires the invitation to negotiate to be made without unjustified delay.
Article 177 provides that a warning may be given by any means the parties agreed, or by any means the law provides for service, including filing a suit or another judicial step. The Law therefore leaves the form of notice to the parties' agreement or to the legal means of service. A party should check its contract's notice clause, time limits and evidence requirements, and keep the correspondence and documents that show the event, its date and its effect on performance.
Contract clauses: exemption and bearing force majeure
The parties may agree to exempt the debtor from damages for non-performance or delay of a contractual obligation, except where it results from the debtor's fraud or gross fault (art 173(1)). An agreement exempting a person from liability for a harmful act is not permitted (art 173(2)). The parties may also agree that the debtor bears the risk of force majeure (art 174).
Article 125 names force majeure only as an example of a cause outside a person's control, alongside the act of a third party or of the injured person, and art 174 lets the parties agree that the debtor bears its risk. The contract should therefore define the events the parties treat as force majeure and state their effect on deadlines, payment and termination, rather than rely on a general phrase.
Effects of rescission and automatic dissolution
When a contract is rescinded or dissolved, the parties return to the position they were in before contracting, and if that is impossible the court may award compensation. If the contract is a continuing one, rescission or dissolution has no retroactive effect, and the court may award compensation where it is warranted (art 111). What was performed before the event, and what was paid for it, therefore needs to be examined.
Lump-sum construction contracts
Where a construction contract is made on an agreed design for a lump sum, the contractor may not claim any increase in the price even if the price of materials, wages or other expenses rises (art 471(1)). However, if the contractual balance collapses because of general exceptional circumstances that could not have been foreseen at the time of contracting and the financial basis of the estimate is undermined, the court, depending on the circumstances and after weighing both parties' interests, may restore the contractual balance, including by extending the performance period or increasing or reducing the price, or may rescind the contract (art 471(3)).
Worked example: a continuing supply contract
Company A undertakes to supply a monthly quantity of a product to Company B for twelve months at a fixed price. In month five two things happen. First, the only road to Company B's site is closed for two months and there is no other way to deliver. Second, the price of a raw material used in production rises sharply in the same month.
On the first event, if it is shown that the cause was outside Company A's control and that delivery became impossible during the two months, the impossibility is temporary in a continuing contract. The obligation lapses for the impossible part and its counterpart, Company B may ask for rescission, and the court may refuse it if the impossible part is of minor importance (art 110(2)). On the second event, a price rise does not make delivery impossible. If the conditions of art 97 are met, that is a general exceptional circumstance not foreseeable when contracting and threatening a heavy loss, Company A may invite Company B to negotiate without unjustified delay, and it remains bound to perform during negotiation. If there is no agreement, the court may reduce the obligation to a reasonable level. If those conditions are not met, that article does not help it. The whole result is subject to the contract's clauses on exemption and on bearing force majeure.
Frequently asked questions
Is a price rise force majeure?
A price rise alone is not impossibility under art 110. Article 97 may apply if it results from general exceptional circumstances that could not be foreseen when the contract was made and performance becomes burdensome so that it threatens a heavy loss. Its effect is renegotiation and then, failing agreement, reduction of the obligation to a reasonable level.
Can the debtor stop performing once it asks to renegotiate?
No. Article 97 provides that asking to negotiate does not entitle the debtor to withhold performance.
Who bears the burden of proving impossibility?
The debtor. Article 294 extinguishes the obligation if the debtor proves impossibility for a cause outside its control, and art 170 bars damages if the debtor proves the non-performance was for such a cause.
What if the impossibility is temporary?
In continuing contracts, the rules on partial impossibility apply to temporary impossibility. The obligation lapses for the impossible part and its counterpart, the creditor may ask for rescission, and the court may refuse it if the impossible part is of minor importance (art 110(2)).
Can the parties agree otherwise?
They may exempt the debtor from damages except for fraud or gross fault, and may agree that the debtor bears the risk of force majeure (arts 173 and 174). An agreement contrary to art 97 is void.
What happens to what was already performed if the contract is rescinded or dissolved?
The parties return to their pre-contract position, and if that is impossible the court may award compensation. In continuing contracts there is no retroactive effect (art 111).
Can a lump-sum contractor claim more when materials rise?
Not under art 471(1). If the contractual balance collapses because of general, unforeseeable exceptional circumstances, the court may restore it, including by increasing the price, extending the period or rescinding (art 471(3)).