Once the works are complete, a decisive phase begins: preliminary acceptance, the warranty year, final acceptance and the final account. The recurring questions are procedural: who calls for acceptance and how fast the entity must move, what happens when the entity itself cannot take the project over, what the inspection record is worth, and who still owes the tests. This page sets out the acceptance procedure in public construction contracts under the Government Tenders and Procurement Law's implementing regulation, together with the warranty year and the rule that acceptance without remarks does not discharge the contractor.

Preliminary acceptance: notice and the fifteen-day committee

In public construction contracts, the works are received preliminarily after the contractor gives notice of their completion, under Article 127 of the implementing regulation. The government entity must form a committee to begin inspection and acceptance within fifteen days of the contractor's notice. The contractor's notice is therefore the trigger, and the fifteen days are the entity's outer limit to start moving.

When the entity cannot receive for its own reasons

If the entity cannot receive the project for reasons not attributable to the contractor, such as something preventing operation or testing or another cause within the entity's responsibilities, a completed inspection record is prepared with the contractor or his representative, inventorying all the executed works. Under Article 127, that completed record counts as preliminary acceptance and as a basis for paying the value of those works and the final statement. The contractor remains responsible for conducting the tests and trial for final acceptance if those reasons disappear during the warranty period. The entity's own blockage therefore does not freeze the contractor's account.

The warranty year runs from preliminary acceptance

Under Article 128 of the implementing regulation, the project in public construction contracts remains under the contractor's warranty for no less than one year from the date of preliminary acceptance. If deficiencies are found in the project after its acceptance, the warranty period for those deficiencies starts from the date of their own acceptance, not from the project's. Each deficiency carries its own clock, so closing a punch list in batches means multiple warranty start dates.

Acceptance without remarks does not discharge

During the warranty year the contractor must maintain, repair and replace whatever defects appear in materials, devices or equipment, and defects in execution, under Article 128. The entity's acceptance of the works without remarks, or its acceptance of deficiencies or non-conforming materials not caught during preliminary acceptance, does not bar that obligation. Unremarked acceptance is no implied discharge. If the contractor does not comply, the entity executes the works at his expense up to the prevailing prices, after warning him by the means it finds appropriate.

When the contract term ends without delivery

If the contract term ends in public construction contracts without the contractor delivering the works, the entity forms a technical committee to inspect the works and prepare a record together with the contractor, under Article 127: an inventory of the executed works, the completion percentage, and the causes and obstacles of the delay. That record fixes the state of the works at expiry and frames what follows.

A note on the restated statute

The provisions taught here come from the Government Tenders and Procurement Law issued by Royal Decree M/128 and its implementing regulation in its fourth consolidated version of April 2024, which predates an amendment of the implementing regulation of 5 June 2026 and is therefore not the complete current text. Royal Decree M/76 restates the statute; it was published in Umm Al-Qura on 4 September 2026 and takes effect 120 days after publication, while works tendered under the current statute remain governed by it, except that the Minister of Finance may apply some provisions of the new statute to them under a mechanism he sets, without prejudice to steps already taken for them. The article numbers cited on this page may change at the commencement of the restated statute and its regulation, so verify the latest official texts before relying on any number.

Common mistakes

  • Treating preliminary acceptance as the end of responsibility, when the warranty year and the repair duty begin exactly there.
  • Letting the fifteen-day window pass without forming the inspection committee after the contractor's completion notice.
  • Leaving the inspection record incomplete when the entity cannot receive for its own reasons, which strips the contractor of his payment basis and the final statement.
  • Forgetting that the contractor still owes the tests and trial toward final acceptance once the entity-side blockage disappears during the warranty period.

Hypothetical example

This is a hypothetical example for illustration; it does not represent the facts of any real case.

A contractor completed a government pumping station and gave notice of completion. The entity formed its committee within fifteen days, but the station could not be operated or tested because the entity's own utility connection was not ready, a cause within its responsibilities. The committee prepared a completed inspection record with the contractor inventorying every executed work. The record counted as preliminary acceptance, and the value of the works and the final statement were paid on it. When the connection was completed during the warranty year, the contractor returned and ran the tests and trial toward final acceptance, as Article 127 requires.

Frequently asked questions

When does the warranty year start in government construction contracts?

From the date of preliminary acceptance, under Article 128 of the implementing regulation. Deficiencies found after acceptance start their own warranty period from the date they are accepted.

Does acceptance without remarks discharge the contractor from defects?

No. Article 128 of the implementing regulation provides expressly that the entity's acceptance of the works without remarks does not bar the contractor's warranty and maintenance obligation for what was not caught during preliminary acceptance.

How fast must the entity move after the completion notice?

The entity forms a committee to begin inspection and acceptance within fifteen days of the contractor's notice of completion, under Article 127 of the implementing regulation.

What if the entity cannot receive the project for its own reasons?

A completed inspection record is prepared with the contractor, and it counts as preliminary acceptance and as a basis for paying the value of the works and the final statement, under Article 127.

Who runs the tests when the entity-side blockage disappears?

The contractor. He remains responsible for conducting the tests and trial for final acceptance if the reasons that prevented acceptance disappear during the warranty period.

What happens when the term ends without delivery of the works?

The entity forms a technical committee that prepares, with the contractor, a record inventorying the executed works, the completion percentage and the causes of delay, under Article 127 of the implementing regulation.

This page is general information.

This article is general legal information for educational purposes, not legal advice, not an opinion on any specific case, and not a promise of outcome in any claim or compensation. Laws and instructions may change, and their application differs with the facts and documents of each case. Before taking any step or filing any request, consult a lawyer licensed in Saudi Arabia and verify the latest official texts and instructions.