Which provisions apply
The rules are in Federal Law No. 11 of 2023 Concerning Procurement in the Federal Government, in force from 1 December 2023: Articles 17 to 22, 24 to 27, 29 and 38.
Announcement of the tender
The federal agency offers its procurement in a public tender, unless the conditions of the other procurement methods set by the executive regulations are met. The announcement is published on the electronic or digital procurement system or another system used by the federal agency, and participating suppliers must be able to view all relevant tender documents (Article 17). The announcement must contain all the information participating suppliers need to prepare and submit their bids, including the name of the federal agency, the procurement method, the description and specifications of what is required, the contract terms and duration, the evaluation mechanism and criteria with the weight of each criterion, and the deadline and procedure for submitting bids on the procurement system (Article 18).
Time to bid and inquiries
Participating suppliers must be given enough time to respond to the announcement. The federal agency sets that time realistically. The bidding period may never be shorter than the periods set by the executive regulations, and the agency may extend it. If the agency issues clarifications or amendments, it may extend the deadline so that suppliers can take them into account (Article 19).
Participating suppliers may raise inquiries and request reasonable and necessary data to evaluate the tender within the period set by the announcement. The agency must answer all reasonable inquiries and requests urgently and may extend the deadline if it cannot answer in time. All competing suppliers must be told of the inquiries received and the answers given, but not the source of an inquiry or the confidential or sensitive commercial information of a supplier. A meeting with participating suppliers may be held before the final responses at the request of any of them, and its notes must be recorded and made available to all participating suppliers (Article 20).
Cancelling or amending the tender
The federal agency may cancel or amend the tender procedures or announcement at any time before the deadline for responses, under the conditions and procedures set by the executive regulations, and no bid may be opened after a cancellation decision. It must publish any cancellation or change on the procurement system and inform all participating suppliers at the same time. It must give suppliers that have already bid enough time to respond to amendments and may extend the deadline for that purpose (Article 21).
Evaluation of bids
Bids are evaluated transparently and fairly using criteria related to the subject of the procurement, which may include financial cost, operating and maintenance cost, delivery and completion time, conformity with the required specifications, payment terms and guarantees, and the supplier's experience, reputation, competence and professionalism. Non-price criteria must be objective, proportionate to the procurement and, as far as possible, quantitatively measurable. The announcement must state the criteria, the evaluation method and the weight of each criterion, and bids are evaluated on those criteria, method and weights. No criterion or procedure that was not announced may be used (Article 22).
A bid is not excluded because of a low price unless the federal agency is satisfied that the price is significantly below the estimated cost and the prevailing market prices, in a way that may affect the supplier's ability to meet its contractual obligations. The agency must first discuss the price with the supplier, ask for a breakdown of the components of the bid and an explanation of the low price, and may exclude the bid only if it is not convinced of the supplier's ability to perform. It must inform the supplier of the exclusion decision and the reasons (Article 25).
Exclusion of a supplier
The federal agency may exclude a participating supplier from the tender if the bid does not meet the minimum basic requirements in the announcement, if the supplier failed in carrying out a previous procurement offered by a federal agency or a case of stopping dealings with suppliers set by the executive regulations applies, if the supplier has not met its financial obligations to the government such as taxes and fees, if the supplier did not keep the timelines in the request for bids, or for any other reason set by the executive regulations. The agency must inform the excluded supplier of the decision and the reasons on which it is based (Article 24(1) and (3)).
Award and notice
The tender is awarded under the procedures set by the executive regulations and on the evaluation criteria in the announcement, to the participating supplier whose bid meets the contract requirements and conditions and shows the capability needed to carry out the contract, and achieves the public interest and the best public value over the whole contract period (Article 26). After the evaluation and the award decision, all participating suppliers must be informed that the tender was awarded to the winning supplier. If the winning supplier is late in submitting the required documents or signing the contract without an acceptable excuse within the period set by the executive regulations, the federal agency may, after warning it, cancel the award and award the tender to the second best participating supplier or decide to re-tender (Article 27).
Reasons for non-selection
Without prejudice to the right to file a grievance, a participating supplier that was not selected may ask the federal agency to explain the reasons why it was not chosen, including the strengths and weaknesses of its bid. The agency must answer within the period set by the executive regulations (Article 29).
The grievance
Every participating supplier has the right to file a grievance before the federal agency against any decision the agency took before the award decision, within 5 business days from the date it was notified of the decision. A supplier may also file a grievance against the award decision within 5 business days from the date the award decision was issued (Article 38(1)).
The federal agency must decide the grievance impartially within the period set by the executive regulations. If that period passes without a response, this counts as a rejection of the grievance. The executive regulations set the mechanisms and controls for grievances and responses, the related time limits, the procedures and the authority competent to decide (Article 38(2) and (3)).
Frequently asked questions
How long does a supplier have to file a grievance?
5 business days from the date it was notified of a decision taken before the award, and 5 business days from the date the award decision was issued for a grievance against the award (Article 38(1)).
What if the federal agency does not answer a grievance?
If the period set by the executive regulations passes without a response, this counts as a rejection of the grievance (Article 38(2)).
Can the federal agency evaluate bids on criteria that were not announced?
No. Bids are evaluated on the criteria, method and weights announced in the tender announcement, and no criterion or procedure that was not announced may be used (Article 22).
Can a bid be excluded only because its price is low?
Not unless the federal agency is satisfied that the price is significantly below the estimated cost and the prevailing market prices in a way that may affect the supplier's ability to perform, after discussing it with the supplier and asking for a breakdown and an explanation (Article 25).